Evidence profile · Foothills County

Beacon Foothills AI Data Center Hub

A proposed data centre campus east of High River.

Illustrative landscape · Sevgi Gümüş / Pexels
← Alberta data centre project list
Developer Beacon Data CentersView on project map ↗

NE and SE 09-19-28 W4M, east of High River · Map precision: Approximate area

Planning bylaws are approved. A project-specific development permit has not been verified, and the final power and water designs remain unresolved.

Campus power400 MWProposed capacity, not operating use [1]
Water demandNot disclosedCooling and supply unconfirmed [4]
Sound levelsNot publishedNo project-specific model found [3]
Operating jobs300 projectedProponent estimate, not a commitment [6]
EmissionsNot disclosedGeneration fuel also unresolved [6]
Subject lands279.5 acresRedesignated to Business Park [3]

Where it stands

Municipal planningBylaws approvedFebruary 26, 2025 [3]
Development permitNot verifiedSeparate decision required [5]
Grid connectionStage 2 requestAlberta Electric System Operator (AESO) P2926 [7]

Separate approval tracks, not a construction progress bar. Construction authorization and a binding schedule have not been verified. Record last verified 2026-11-03.

Want to get involved?

The recorded public hearing took place January 29, 2025. This profile’s existing sources do not establish a current participation window. See the approval and participation record ↓

Federal principles: Beacon Data Centers is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Power and emissionsCampus capacity, generation, grid supply, and unresolved emissions

The proposal describes a 400 MW data centre campus. That is planning-stage capacity, not approved or operating demand. Alberta Major Projects separately reports 400 MW of proposed on-site generation, while the Alberta Electric System Operator (AESO) records a 400 MW grid-load request. These three figures describe different parts of the proposal and must not be added together. [1][6][7]

AESO’s September 2026 list places request P2926 at Stage 2, with its in-service date under review. A request is not an approved connection, contracted or guaranteed supply, construction, or measured load. Final connection studies, transmission facilities, utility agreements, construction timing, and the service date remain unresolved. [7]

The reviewed sources do not establish whether on-site generation would normally supply the full campus, how often grid power would be imported or exported, or whether the two supply paths would be alternatives or work together. [1][6][7]

The generation fuel, equipment, air emissions, greenhouse-gas estimate, regulatory applications, and approval path have not been published in the reviewed record. The land-use definition allows supporting power-generation facilities, but no project-specific backup fleet, capacity, fuel storage, or emissions filing was found. [6][2][3]

What would clarify the impact: a project-specific power design showing how generation and grid supply would work together, along with the associated emissions and approval requirements.

Water, cooling and drainageSupply, demand, wastewater, and stormwater

No reviewed project-specific filing establishes the cooling technology, water source, daily or annual demand, withdrawal, consumption, discharge, or measured use. A campus operating water balance and final wastewater route have not been published. [1][4]

The amended Foothills Crossing Area Structure Plan identifies future County piped service from Aldersyde as the most likely long-term solution for the wider plan area. That is a servicing concept, not evidence of reserved capacity or a final Beacon supply agreement. [4]

The plan also contemplates interim on-site options and allows interim development before piped wastewater service is available. A project-specific water and wastewater design has not been published. [4]

The site-specific rules tie the maximum impermeable coverage, such as roofs and paved surfaces, to a professional stormwater management plan. Final pond, discharge, wetland, and construction details remain unresolved. [3][4]

What would clarify the impact: a campus water balance and servicing design showing the source, quantities, cooling method, and wastewater route.

Sound at nearby communitiesRequired noise work and the information still missing

Foothills County requires the later development-permit application to include noise mitigation and monitoring where Alberta Utilities Commission (AUC) Rule 012 does not apply. No project-specific noise model, predicted level at nearby homes or other assessment locations, or final mitigation design was found in the reviewed record. [3]

What remains unresolved: the sound levels neighbours could experience and the measures proposed to limit and monitor them.

Land, wetlands and wildlifeSubject lands, building limits, and environmental studies

The subject lands total 279.5 acres east of High River: 129.51 acres in part of NE 09-19-28 W4M and 149.99 acres in part of SE 09-19-28 W4M. The site-specific maximum structure height is 18 metres. [3]

The final number, height, footprint, and phasing of data halls remain unresolved. Municipal and provincial sources describe the building program differently, so the planning limits do not establish the final site layout. [1][6]

The County staff report records a Level 1 Environmental Site Assessment and a biophysical inventory covering the subject lands. The inventory examines habitat, plants, and wildlife. These studies support the application; they are not final construction approval. [1]

The amended area plan reports that the 2024 assessment found no indications of potential species at risk. It also maps wetlands, a sensitive raptor range, and a sharp-tailed grouse survey area. Wetland assessment and, in specified circumstances, wildlife surveys are required before later development can proceed. [4]

What remains unresolved: final wetland treatment, further wildlife surveys where required, mitigation, and permit conditions. The initial assessments do not settle all effects of construction.

Indigenous contextTreaty geography and the limits of the available consultation record

The site is in Treaty 7 territory. This is geographic context; it does not establish which communities may be affected, their positions on the proposal, or whether consultation is adequate. [8]

A complete project-specific Indigenous consultation and engagement record was not found in the reviewed municipal and provincial sources. [8]

Approvals and participationPlanning decisions, remaining permits, and past opportunities to participate

The planning bylaws allow a data centre campus to be considered here as a discretionary use, which requires a separate development-permit decision. They did not issue that permit or authorize construction. A project-specific development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more →, approved site plan, building permit, or construction authorization has not been verified. Separate utility, environmental, power-plant, and connection approvals may also be needed. [3][4][5]

Stantec submitted the combined area-plan amendment and land-use application on Beacon’s behalf in November 2024. The applicant held an open house at the Highwood Centre in High River on December 11, 2024. Foothills County then held the public hearing and gave first reading to Bylaws 05/2025, 06/2025, and 07/2025 on January 29, 2025. [4][2]

On February 26, 2025, Council passed second and third readings of all three bylaws. Bylaw 05/2025 amended the Foothills Crossing Area Structure Plan to allow a business park that may accommodate a data centre campus and related uses. Bylaw 06/2025 added a campus definition that includes supporting power generation, substations, maintenance, offices, and security buildings. Bylaw 07/2025 redesignated the subject lands from Agricultural to Business Park and made a campus a discretionary use. [3][4]

A complete development-permit application must include a fire-prevention program and a dynamic emergency-response plan, as well as the noise mitigation and monitoring requirements described under Sound at nearby communities. The later site plan and permit conditions will matter to what neighbours ultimately see and hear. [3]

The open house and hearing are historical opportunities. The sources reviewed for this profile do not establish a current participation window. The County’s area-plan page is linked below so readers can return to the municipal record. [5]

Company and commitmentsDeveloper, projected jobs and investment, and delivery commitments

Beacon Data Centers is the developer named in this profile. Alberta Major Projects lists a $4.0 billion estimate and 300 projected operating jobs. Its description also refers to Beacon’s broader six-campus program. ADCW has not verified a project-specific cost breakdown. [6]

The employment figure is a proponent projectionProponent projectionA forecast, target, estimate, or promised future outcome from the company proposing the project.The label identifies whose projection it is. It does not turn a future claim into an independently verified result or an enforceable approval condition.Learn more →, not observed employment or a binding local-benefit commitment. The cost and employment estimates do not establish what benefits would ultimately be delivered locally. [6]

Committed customers, financing, a final investment decision, contractor awards, equipment orders, and binding construction dates have not been disclosed in the reviewed record.

SourcesOriginal documents and publication details

Source record

Company disclosures establish what the company said, not independent verification of projected outcomes.

  1. Beacon data centre public hearing staff reportFoothills County · Municipal record · 2025-01
  2. Council minutes: January 29, 2025Foothills County · Municipal record · 2025-01-29
  3. Council minutes: February 26, 2025Foothills County · Municipal record · 2025-02-26
  4. Foothills Crossing Area Structure Plan, 2025 amendedFoothills County · Municipal record · Amended 2025-02-26
  5. Foothills Crossing Area Structure PlanFoothills County · Municipal record · Accessed 2026-08-23
  6. Beacon Foothills AI Data Center HubGovernment of Alberta Major Projects · Government database · Accessed 2026-08-23
  7. Connection Project ReportingAlberta Electric System Operator · Regulator · November 2026 list; updated 2026-11-03; accessed 2026-11-15
  8. Treaty Boundary datasetGovernment of Canada Open Government Portal · Government database · Modified 2026-06-29