Beacon Heartland AI Data Center Hub
A proposed 800 MW data centre campus with a conditionally approved 920 MW natural-gas power plant east of Gibbons.
The AUC approved the power plant with conditions on October 23, 2026. It did not approve the data centre or a grid connection. Final design, noise, emergency-response, and financial-security requirements remain; construction and operation are unverified.
Where it stands
Separate approval tracks, not a construction progress bar. Record last verified 2026-10-26.
The AUC issued its decision on October 23, 2026. Separately, the County grading notice has an appeal deadline of November 12, 2026, with restricted eligibility as explained in the approvals topic. The approvals topic explains the conditions, remaining filings, and official records; the Indigenous topic distinguishes Samson Cree's opposition from the AUC's consultation finding. See the approval and participation record ↓
Federal principles: Beacon Data Centers is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →
Power and emissionsCampus demand, electricity supply, and emissions evidence
The AUC approved 200 natural-gas engines, each nominally 4.6 MW, arranged in 40 modules for 920 MW of generating capability. Approximately 800 MW would normally supply the proposed data centre. The approval holder is Northbridge Power GPC Inc., general partner of Heartland Power Generation LP. The future grid connection and associated transmission facilities require separate regulatory applications.
Important distinction: The AUC found the power plant's effects acceptable with mitigation, commitments, and regulatory oversight. It acknowledged regional fine-particle concentrations above Alberta's objectives and the plant's additional emissions. Its decision assessed the plant as proposed, without assuming future carbon capture, hydrogen blending, or offsets would be implemented.
Proposed data centre load: 800 MW. Four proposed data halls rated at 200 MW each. This is full-build capacity, not operating demand. [7][12] Proponent statement
Approved power plant: 920 MW. AUC Approval 30518-D02-2026 covers 200 approximately 4.6 MW natural-gas engines in 40 modules. The approximately 800 MW data-centre supply is distinct from total generation capacity. [4][5] Public record
Regional fine-particle concentrations: ModelledModelled versus measuredA modelled result is a prediction based on inputs and assumptions. A measured result comes from observations or instruments under particular conditions.A prediction is not verified operating performance. Check the location, period, operating scenario, and what the reported number actually represents.Learn more → at 198%–213% of Alberta objectives. The AUC's October 23, 2026 decision reports these modelled maximum concentrations, largely attributed to existing background sources, with a 0.2%–0.4% project contribution to the total. These concentration figures differ from the plant's share of regional emissions by mass. The AUC accepted the contribution in light of environmental oversight, regional frameworks, and monitoring commitments; these are not measured operating results. [4] Public record
Natural-gas demand: Up to 218 TJ/day. The federal filing's full-capacity estimate. The dedicated lateral route and approvals remain in development. [12] Proponent projection
Maximum annual GHG estimate: 4.401 million tonnes CO₂e. The proponent's estimate assumes 800 MW output at 100 per cent utilization. Environment and Climate Change Canada characterized the operating emissions as high and recommended full consideration of mitigation. This is a forecast, not measured emissions. [12][17] Proponent projection
Carbon capture: No committed system. The AUC considered the plant as proposed. It did not assume future hydrogen blending, offsets, or carbon capture would occur because implementation remains uncertain. The approximately 4.401 million tonnes CO₂e/year figure remains a proponent forecast, not measured emissions. [4][12] Public record
Estimated yearly air pollution: 471 t NOₓ, 902 t CO, and 120 t fine particles. If the plant runs continuously, the developer estimates its smokestacks would release these yearly totals of nitrogen oxides, carbon monoxide, and fine particles. These figures describe pollution leaving the stacks, not the amount people would breathe at ground level, and they are estimates rather than measured results. [12][9] Proponent projection
Air pollution from Heartland alone: Developer predicts levels below Alberta limits. Looking only at Heartland, the developer's model predicts that the highest ground-level concentrations would reach 23% of Alberta's limit for nitrogen dioxide, 1.2% for carbon monoxide, and 44% for fine particles. Health Canada said meeting those limits alone does not settle the question of health risk. It recommended looking at combined pollution from the region, comparing results with health-based benchmarks, monitoring air quality, and reducing emissions where practical. [9][18] Proponent projection
Heartland's share of regional fine-particle emissions: About 1 in every 10 tonnes in the project case. Across the existing, approved, and proposed sources counted in the model, Heartland would contribute 0.327 tonnes per day, or 10% of fine-particle emissions. That is its share of emissions across the region, not its share of pollution at any one location. This is why Heartland can account for 10% overall while barely changing the model's worst existing hotspots. [9] ADCW context
Grid connection: Separate applications required. The AUC's October 23, 2026 decision says the future grid connection and associated transmission facilities have not yet been designed. The 920 MW generation approval does not grant a grid connection. [4] Public record
Gas pipeline: Separate approval path. The proponent expects a dedicated lateral from the NGTL and ATCO system about 0.5 km east of the site. The route remains in development, and the pipeline operator would obtain separate approvals. [12] Proponent statement
What remains unresolved
The final natural-gas lateral route, capacity, operator application, approval status, and construction schedule remain unresolved.
The AUC's October 23, 2026 decision does not approve a grid connection. It says the final connection and associated transmission facilities have not yet been designed and will be considered through separate regulatory applications as required.
No committed carbon-capture system, capture rate, construction schedule, or funding is identified. The AUC assessed the plant without assuming future capture or other proposed pathways would be implemented.
The Government of Alberta Major Projects page lists 960 MW in the earlier reviewed record, while the new AUC approval confirms 920 MW of generation intended to supply approximately 800 MW to the data centre. The different registry figure remains unreconciled.
Water, cooling, and drainageSupply, demand, wastewater, and servicing
Projected campus demand: Earlier estimate: up to 1,500 m³/day. The earlier federal project description projects up to 1.5 million litres per day for the combined data-centre and power-generation campus. This is a planning estimate, not measured use. The newer plant-only estimate does not establish a revised campus total or final data-centre cooling demand. [12][22][4] Proponent projection
Power-plant water estimate: 0–1 m³/day; up to 365 m³/year. The AUC's October 23, 2026 decision gives this updated estimate, equivalent to up to 1,000 litres per day, and describes closed-loopClosed-loop coolingCooling fluid circulates repeatedly through a contained loop instead of being routinely discharged after one pass.That describes the loop, not the whole site's water use. A separate heat-rejection system can still use water, and filling, maintenance, and leaks also matter.Learn more → glycol cooling. The earlier federal project description allowed approximately 100 m³/day for the plant. The reduction applies to the plant alone. [4][12] Public record
Water agreement and capacity: Municipal plant supply; campus capacity unconfirmed. The AUC decision describes potable supply through Sturgeon County's existing municipal system under a water services agreement, without a new allocation, separate diversion, or change to existing licensees' allocations. It does not publish the executed agreement or confirm infrastructure capacity for the full campus. [4][12] ADCW context
Wastewater: Municipal system if feasible. The proponent proposes Sturgeon County's sanitary system where capacity is available, with approved alternatives otherwise. Final acceptance, volumes, and disposal arrangements are not published. [12] Proponent statement
What remains unresolved
A reconciled full-campus water balance, final data-centre cooling design, infrastructure capacity, executed servicing agreements, and wastewater acceptance remain unconfirmed.
Sound at nearby communitiesAssessment evidence, controls, and remaining questions
The decision's revised assessment predicts 45.8 dBA by day and 38.4 dBA at night at L1, an unoccupied location on the 1.5 km criteria boundary. The AUC reports no dwellings within 1.5 km of the project boundary. These replace the older R1 figures as the current assessment context; final design and post-construction verification remain required.
Current sound-assessment context: No dwellings within 1.5 km. The AUC's October 23, 2026 decision reports no dwellings within 1.5 km of the project boundary and assesses compliance at unoccupied L1. Earlier federal advice described a residence about 200 m north of the project area. The documents do not explain that difference; the older distance is not treated as the current receptor finding. [4][18] ADCW context
Current cumulative sound model: 45.8 dBA day; 38.4 dBA night at L1. The revised assessment predicts compliance with 50 dBA daytime and 40 dBA nighttime limits at unoccupied L1 on the 1.5 km criteria boundary. Residences R2–R5 are farther than 1.5 km and were assessed for information. These are modelled results, not measurements. [4] Proponent projection
Final design and mitigation: Combined plant and data-centre assessment required. The AUC approval requires a final project update at least 90 days before construction, a final cumulative noise assessment covering concurrent plant and data-centre operation, and implementation of the relied-upon mitigation or measures with equal or better acoustic performance. A mitigation report is due within 30 days after concurrent operation begins. [4][5] Public record
Post-construction verification: Field study within six months of concurrent operation. The AUC approval requires near-field measurements of representative principal plant and data-centre equipment, an updated cumulative assessment at L1 and other assessed locations, and a mitigation plan with timelines if needed. The AUC did not require the proposed survey at R2 and R5 because it would not verify compliance at L1. [4][5] Public record
Earlier nearby-receptor record: Different from the decision's assessment. The earlier federal assessment used R1 and the earlier federal advice described a residence about 200 m north of the project area. The decision instead reports no dwellings within 1.5 km of the project boundary. ADCW has not established why the receptor context changed and does not combine the two assessments. [4][13][18] ADCW context
Land, wetlands, and wildlifeSite area and the available environmental record
Campus area: 320 acres. Beacon's current project page rounds the site to 320 acres. The federal filing describes a 317-acre campus and a 32-acre power-plant footprint. [22][12] ADCW context
Woodland loss and wildlife mitigation: Habitat loss acknowledged; approval granted. The AUC recognized that loss of wooded habitat is an adverse effect not fully addressed by describing it as previously cultivated. It found the loss did not justify refusal, considering the Industrial Heartland location and mitigation. Commitments include clearing outside the annual migratory breeding-bird period of April 15 to August 31. The AUC also found cumulative effects manageable through project measures and regional frameworks. [4] Public record
Wetlands in project area: 9.469 ha of waterbody impacts. The AUC's October 23, 2026 decision records removal of 16 wetlands, 13 ephemeral waterbodies, and three ephemeral drainages. Five wetlands and one ephemeral drainage at the north end would be retained. These are the decision's impact figures, distinct from the older inventory of 20 wetlands and 13.3 ha of wetland habitat. [4][12] Public record
Wetland approvals: Water Act approval confirmed by AUC. The AUC's October 23, 2026 decision confirms that Alberta Environment and Protected Areas provided a Water Act approval for wetland impacts requiring compensatory offsets. The underlying approval number, full conditions, and evidence of payment are not included in these documents. This does not establish an EPEA approval. [4] Public record
Species-at-risk observation: Western toad at WL19; 100 m setback. The decision records relocation of the soil stockpile to maintain the full recommended 100 m western toad setback at WL19, with more impacts shifting to WL15. Commitments include prioritizing upland stockpiling, wetland topsoil salvage if WL15 is used, environmental inspection, documentation, and ongoing engagement with Samson Cree on WL19. [4] Public record
Federal ecological advice: Cumulative habitat risk flagged. Environment and Climate Change Canada identified wetland drainage, vegetation clearing, lighting, spills, and cumulative habitat effects as potential risks to migratory birds and species at risk in the Industrial Heartland region. These are federal expert concerns and mitigation advice, not findings that the effects will occur. [17] Public record
What remains unresolved
The AUC confirms a Water Act approval for wetland impacts, but the underlying approval number, full monitoring and compensation conditions, and payment evidence are not in these documents. A final project-specific EPEA approval remains unverified.
Compliance with wetland and wildlife commitments, including protection of WL19 and the 100 m western toad setback, tree-clearing timing, and post-construction monitoring, remains to be verified.
Indigenous contextTreaty geography, engagement, and consultation evidence
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
AUC consultation finding: Duty triggered and fulfilled for Samson Cree. Samson Cree Nation remained opposed and requested denial. The AUC found the likely adverse effect on the exercise of its rights low, consultation required no higher than the middle of the spectrum, and the Crown's duty fulfilled. This is the AUC's finding, not Samson Cree's agreement. [4] Public record
Participation at the decision: Four Indigenous groups withdrew with no objection. Ermineskin Cree Nation, Lac Ste. Anne Métis Community Association, Louis Bull Tribe, and Whitefish (Goodfish) Lake First Nation #128 withdrew their participation. Samson Cree remained active. Ongoing engagement and commitments remain relevant after the decision. [4] Public record
Treaty geography: Treaty 6 territory. The project lies in Treaty 6 territory. This is geographic context and does not by itself determine consultation adequacy or effects on rights. [21][15] ADCW context
Provincial pre-consultation: ACO said consultation was not required. The proponent's federal response says Alberta's Aboriginal Consultation Office reached this conclusion for the Water Act pre-consultation request because of the proposed activities and private-land context. The proponent says it nevertheless notified 23 Indigenous communities. [15] Proponent statement
AUC participants with standing: Five Indigenous groups. Lac Ste. Anne Métis Community Association, Samson Cree Nation, Whitefish (Goodfish) Lake First Nation #128, Ermineskin Cree Nation, and Louis Bull Tribe received standing in the power-plant proceeding. [8] Public record
Federal issues list: Rights and cumulative effects required clarification. IAAC's issues list asked the proponent to clarify meaningful engagement, Section 35 rights, cumulative effects on traditional land use, and meaningful long-term economic benefits. [14][16] Public record
Economic-benefit evidence disputed: AUC gave less weight to specific forecasts. Samson Cree challenged the late-filed economic and fiscal assessments and had no opportunity to test them in an oral hearing. The AUC gave less weight to specific forecasts while accepting employment and economic activity as benefits. It also gave less weight to benefits dependent on the data centre, future grid connection, or other facilities not before it. [4][11] Public record
Indigenous procurement: No formal policy confirmed. Samson's submission cites a proponent response stating that no formal Indigenous procurement policy had been established, despite general commitments to seek employment and contracting opportunities. [11][15] Public record
What remains unresolved
The AUC found the duty to consult Samson Cree fulfilled, while Samson Cree requested denial. Implementation of ongoing engagement, habitat-protection, information-sharing, and incident-notification commitments remains to be verified.
Approvals and participationSeparate decisions, public participation, and the recorded timeline
The AUC approval authorizes the power plant subject to conditions. It does not approve the data centre or replace environmental, municipal, pipeline, or grid-connection decisions. The AUC confirms a Water Act approval for wetland impacts, while a final project-specific Environmental Protection and Enhancement Act (EPEA) approval is not established by the October 23, 2026 decision and approval.
AUC status: Approved with conditions. Decision 30518-D01-2026 and Approval 30518-D02-2026 were issued October 23, 2026. They authorize the power plant, not the data centre or a grid connection. [4][5] Public record
County permit confirmation: Both permits confirmed as Beacon Heartland. Sturgeon County confirmed in written correspondence to ADCW on October 26, 2026 that both DP-26-0221 and DP-26-0241 are for Beacon's Heartland AI Hub. DP-26-0241 is the full grading permit; DP-26-0221 is limited to topsoil stripping and stockpiling. [1][2] Public record
Topsoil preparation permit: DP-26-0221 issued. The County issued this permit on August 27, 2026 for topsoil stripping and stockpiling at 56205, 56207, and 56211 Range Road 223 (SW and NW-15-56-22-W4M). Its stated effective date is September 17, 2026. The notice does not establish that physical work occurred. [1] Public record
Phased site-grading permit: DP-26-0241 issued; not yet effective. The County issued this permit on October 22, 2026 for grading for phased development of a data-processing facility at 56211 Range Road 223 (NW-15-56-22-W4M). The County confirms the required grading approvals have been obtained, including applicable provincial approvals, and the work may proceed in accordance with the approved permit conditions. The public notice gives November 12, 2026 as the full grading permit's effective date. Approvals for future development phases remain separate. Physical work remains unverified. [2] Public record
Grading-permit appeals: November 12, 2026; eligibility restricted. The County notice directs appeals to the Land and Property Rights Tribunal. For this permitted use, it limits appeals to the applicant or an affected person where the Land Use Bylaw was relaxed, varied, or misinterpreted. ADCW has reviewed the County notices and written clarification, but not the complete permit conditions. [2] Public record
Before construction: Final update and emergency plan at least 90 days ahead. The AUC approval requires final equipment and design information, a combined noise assessment, and a project-specific emergency response plan reviewed with Sturgeon County Emergency Services and other authorities identified through that review. The plan must provide for notifying Samson Cree of incidents that could affect North Saskatchewan River water quality. [4][5] Public record
Construction completion deadline: July 31, 2029 unless changed by AUC. The AUC approval sets this deadline. Completion must be reported within 30 days. The decision records the proponent's earlier Q4 2026 construction-start and Q4 2027 in-service targets, but the approval does not establish either has occurred or remove the pre-construction filing requirements. [4][5] Public record
Municipal permit: Master site permit amended. Sturgeon County says it approved Beacon's data-centre master site development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more → in 2025 and amended it in February 2026 to include a gas-to-electric generation facility. Permit conditions and later construction authorizations remain separate. [20][22] Public record
AUC proceedingAUC proceedingA proceeding is the Alberta Utilities Commission's formal record for reviewing an application, including evidence, submissions, and a decision when issued.A proceeding number helps locate the record. The existence of a proceeding does not mean the application has been approved.Learn more →: 30518: power plant approved with conditions. Decision 30518-D01-2026 grants Northbridge Power GPC Inc. Approval 30518-D02-2026 to construct and operate the 920 MW plant. The approval is not transferable without AUC authorization, and substantive design changes need prior approval. It does not establish that construction has begun. [4][5] Public record
Federal planning decision: No further impact assessment required. IAAC concluded that possible federal effects would be limited or addressed through existing laws. The March 9 decision did not approve the project or replace provincial, municipal, pipeline, or utility approvals. [16] Public record
Provincial environmental approval: EPEA approval required. The AUC application says an Environmental Protection and Enhancement Act application was being submitted concurrently. A final project-specific approval was not found in the reviewed public sources. [7][12] ADCW context
Initial public outreach: 18 landowners within 2 km. The federal filing says introductory packages went to approximately 18 landowners and an open house was held in Gibbons on November 18, 2025. Later federal-registry comments include concerns about the narrow notification radius, water, noise, land, and cumulative effects. [12][19] ADCW context
Recorded timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
2025. Sturgeon County approved a master site development permit for Beacon's proposed data centre, subject to conditions. [20] Public record
November 18, 2025. Beacon held an open house at the Gibbons Community Cultural Centre. [12][20] Proponent statement
December 19, 2025. Heartland Power Generation LP filed its 920 MW thermal power-plant application with the AUC. [7][6] Public record
February 2026. Sturgeon County says the master site development permit was amended to include a gas-to-electric generation facility. [20] Public record
March 9, 2026. IAAC decided that no further federal impact assessment was required. The decision was published March 10 and was not project approval. [16] Public record
March 27, 2026. The AUC issued its notice establishing a written hearing and offering oral Indigenous Knowledge sessions to groups with standing. [8] Public record
July 31, 2026. The AUC's evidentiary record closed for Proceeding 30518. [10] Public record
August 7, 2026. The AUC confirmed that a decision would be issued by October 29, 2026 under its performance standard. [10] Public record
August 27, 2026. The County issued topsoil permit DP-26-0221 for stripping and stockpiling at the Beacon Heartland site, as confirmed by the County on October 26, 2026. [1][3] Public record
September 17, 2026. Stated effective date for topsoil permit DP-26-0221. [1] Public record
October 22, 2026. The County issued full grading permit DP-26-0241 at NW-15-56-22-W4M for Beacon Heartland, as confirmed by the County on October 26, 2026. [2][3] Public record
October 23, 2026. The AUC approved the 920 MW power plant with conditions through Decision 30518-D01-2026 and Approval 30518-D02-2026. The data centre and future grid connection remain separate. [4][5] Public record
November 12, 2026. Stated effective date and restricted appeal deadline for grading permit DP-26-0241. [2] Public record
Fall 2027. Beacon targets initial operations, subject to all remaining approvals, construction, utility work, and commercial decisions. [22] Proponent projection
What remains unresolved
Completion of the final project update, final cumulative noise assessment, emergency response plan, and AUC-approved reclamation security arrangement is not established. Construction and operation are not verified.
Company and commitmentsScale, projected benefits, and delivery commitments
Direct permanent jobs: About 55–110 in earlier campus estimate. The earlier federal response estimates 15–30 power-plant jobs and 40–80 data-centre jobs. The AUC decision repeats 15–30 permanent power-plant jobs and 150–300 construction jobs. It gives less weight to specific economic forecasts because Samson Cree Nation could not test the late-filed assessments. These are estimates, not hiring commitments. [4][15] ADCW context
Target initial operation: Q4 2027. The decision records the proponent's fourth-quarter 2027 target. The AUC approval requires power-plant construction to be completed by July 31, 2029 unless the AUC authorizes otherwise. That deadline is not a guaranteed opening date. Final project and emergency-response filings are due at least 90 days before construction. [4][5] Proponent projection
Who pays for cleanup?: 5% by year one; fully funded by year 20. The AUC approval requires AUC approval of the financial-security arrangement, annual increases to full estimated cleanup cost by the end of year 20, third-party cost updates every five years without deducting salvage value, and security until a reclamation certificate is issued. Material changes must be reported. The AUC questioned the proposed affiliated beneficiary and requested further consideration of County or independent holding arrangements; the final beneficiary remains unresolved. [4][5] Public record
Project overview
The Alberta Utilities Commission (AUC) approved Beacon Heartland's 920 MW natural-gas power plant with conditions on October 23, 2026. The approval covers 200 gas engines intended to supply approximately 800 MW to the proposed co-located data centre; it does not approve the data centre itself or its future grid connection. The decision updates the water and noise evidence, confirms a Water Act approval for wetland impacts, and requires further design, emergency-response, and reclamation-security filings. Construction and operation are not established by these documents. Sturgeon County confirmed on October 26, 2026 that both site-preparation permits relate to Beacon Heartland and the required grading approvals have been obtained. The public notice gives November 12, 2026 as the full grading permit's effective date; work remains subject to its approved conditions.
What remains unresolved
A final investment decision, committed data-centre customers, financing structure, equipment orders, and binding construction schedule were not found in the reviewed public record.
Employment claims have different scopes. The AUC accepted employment benefits but gave less weight to specific forecasts; independently tested campus-wide outcomes and binding hiring commitments remain unverified.
The final reclamation-security beneficiary, amount, instrument, and protection against insolvency require further AUC review. Security is scheduled to reach the full estimated cleanup cost only by the end of year 20.
Unresolved questions are retained within each relevant topic above.
SourcesOriginal documents and publication details
Source record
Company disclosures establish what the company said, not independent verification of projected outcomes.
- Topsoil stripping and stockpiling permit DP-26-0221Sturgeon County · Municipal record · 2026-08-28
- Phased site-grading permit DP-26-0241Sturgeon County · Municipal record · 2026-10-22
- Beacon Heartland Initial Project Description SummaryHeartland Power Generation LP / Impact Assessment Agency of Canada · Federal filing · 2025-12-28
- Decision 30518-D01-2026: Heartland power plant approval with conditionsAlberta Utilities Commission · Regulator · 2026-10-23
- Approval 30518-D02-2026, Appendix 1: 920 MW Heartland power plantAlberta Utilities Commission · Regulator · 2026-10-23
- Beacon AI Centers – Heartland Project Thermal Power Plant ApplicationAlberta Utilities Commission · Regulator · Updated through 2026-08-04
- Beacon Heartland application summary, Application 30518-A001Heartland Power Generation LP / Alberta Utilities Commission · Regulatory filing · 2025-12-19
- Notice of hearing: Proceeding 30518Alberta Utilities Commission · Regulator · 2026-03-27
- Proceeding 30518 filing X0007: Air Quality AssessmentStantec for Heartland Power Generation LP / Alberta Utilities Commission · Regulatory filing · 2025-12
- Proceeding 30518 filing X0293: Application complete and decision deadlineAlberta Utilities Commission · Regulator · 2026-08-07
- Proceeding 30518 filing X0289: Samson Cree Nation submission on the fiscal impact assessmentSamson Cree Nation / Alberta Utilities Commission · Regulatory filing · 2026-07-30
- Initial Description of Designated ProjectHeartland Power Generation LP / Impact Assessment Agency of Canada · Federal filing · 2025-12-14
- Beacon AI Centers – Heartland Project Noise Impact AssessmentStantec for Heartland Power Generation LP / Impact Assessment Agency of Canada · Federal filing · 2025-12-09
- Summary of IssuesImpact Assessment Agency of Canada · Federal filing · 2026-02
- Responses to Summary of IssuesHeartland Power Generation LP / Impact Assessment Agency of Canada · Federal filing · 2026-02-25
- Notice of Early Decision with ReasonsImpact Assessment Agency of Canada · Regulator · 2026-03-10
- Environment and Climate Change Canada Federal Authority Advice RecordEnvironment and Climate Change Canada · Federal filing · 2026-01-23
- Health Canada Federal Authority Advice RecordHealth Canada · Federal filing · 2026-01
- Public and Indigenous submissions: Project 90123Impact Assessment Agency of Canada · Federal filing · Updated through 2026-07
- Data Centre DevelopmentSturgeon County · Municipal record · Updated through 2026-08
- Truth & ReconciliationSturgeon County · Municipal record · Accessed 2026-08-19
- Heartland Data Center HubBeacon Data Centers · Company disclosure · Accessed 2026-08-19
- Beacon Heartland AI Data Center HubGovernment of Alberta Major Projects · Government database · Accessed 2026-08-19