Verified project profile
Beacon Indus Data Center Hub
Beacon proposes four 300 MW data halls and a 1.494 GW natural-gas power plant near Indus as part of its announced six-site Alberta portfolio. Rocky View County approved the area structure plan and land-use redesignation in June 2025, but the power plant remains in an active Alberta Utilities Commission proceeding and later municipal development permits are still required.
Project facts
Core scale, approval, employment and schedule information, labelled by the type of evidence available.
Proposed data centre load
1.2 GWFour proposed data halls rated at 300 MW each.
Sources [6]Proposed power plant
1.494 GWThe AUC application covers on-site natural-gas generation for the campus.
Sources [1]Beacon Alberta portfolio
4.5 GW across six sitesBeacon announced up to CA$10 billion in Alberta investment and said sites could energize as early as 2027. These are portfolio-level claims, not a confirmed Indus funding or opening schedule.
Sources [9], [10]Planning area
383 hectaresThe approved area structure plan covers about 946 acres. The federal filing describes a smaller 627.2-acre data-centre campus within the broader planning area.
Sources [3], [6]AUC proceeding
30524The oral hearing is scheduled to begin August 18, 2026.
Sources [1]Employment estimates
About 300 permanent jobsThe company FAQ says more than 1,500 construction jobs, while the federal filing says up to 4,500. The reviewed records do not reconcile the construction estimates.
Sources [7], [6]Target operation
Third quarter of 2027A proponent schedule that remains subject to approvals, construction and commercial decisions.
Sources [6]Energy and emissions
The proposed 1.494 GW power plant is larger than the planned 1.2 GW data centre load. Both figures describe a proposal, not operating capacity.
Data hall demand
Approximately 1,200 MWThe power plant is intended to serve four 300 MW data halls under normal operations.
Sources [1], [6]Reciprocating generation
100 units totalling 460 MWThe filing describes 100 natural-gas engines rated at 4.6 MW each.
Sources [6]Combined-cycle generation
Four generating blocksThe proposed plant combines reciprocating engines with four combined-cycle gas-turbine blocks for 1.494 GW total capacity.
Sources [6]Projected annual generation
About 10,500 GWhThe proponent estimate assumes full campus operation.
Sources [6]Maximum annual GHG estimate
4.784 million tonnes CO₂eThe federal filing's maximum estimate assumes a 1.2 GW load at 100 per cent utilization. It is not a measured result.
Sources [6]Carbon capture
Future-ready design claimedThe filing discusses possible future carbon capture, renewable gas, hydrogen and offsets, but does not commit to a capture system or operating date.
Sources [6]Water
The federal filing projects approximately 1,500 cubic metres of water demand per day. Supply agreements, final infrastructure capacity and measured use are not yet established in the public record. [6]
Projected campus demand
About 1,500 m³ per dayThe filing says water would come from the regional or municipal system through Langdon Waterworks.
Sources [6], [7]Cooling design
Air-cooled and closed-loop systemsThe filing says the power systems would not use cooling towers or evaporative cooling.
Sources [6]Power-plant and site use
About 750 m³ per dayThe estimate covers heat-recovery steam-generator makeup, fire protection, domestic use and maintenance within the overall campus projection.
Sources [6]Wastewater
Regional system proposedThe proponent proposes the East Rocky View regional system if feasible, with approved disposal alternatives if capacity or connection is unavailable.
Sources [6]Approval and public process
The provincial power review and Rocky View County's later development-permit process are separate. Approval in one process does not replace the other.
Municipal planning
Area structure plan and redesignation approvedRocky View County Council approved the planning framework and Special, Data Centre district on June 17, 2025.
Sources [2], [3]Municipal construction approval
Development permits still requiredThe County states that municipal development permits are required even if the AUC approves the power plant.
Sources [2]County policy update
Later permits are now discretionaryOn July 21, 2026, Council made data-centre campuses discretionary uses and reserved those permit decisions for Council. The separate pause on new S-DAT rezoning decisions does not reverse Beacon's June 2025 redesignation.
Sources [4], [5]AUC review
Active proceedingProceeding 30524 covers the proposed 1.494 GW thermal power plant. The oral hearing is scheduled for August 18, 2026.
Sources [1]County participation
Rocky View County is participatingThe County identifies noise, emissions, water, agricultural land and rural quality of life among its areas of concern.
Sources [2]Public engagement
Open house held April 15, 2025The event formed part of the area structure plan process. Later regulatory processes have separate participation rules.
Sources [3]Timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
- Public record
Beacon held a public open house during the area structure plan process. [3]
- Public record
The federal Initial Project Description was accepted into the public registry. [6]
- Public record
The AUC issued notice for Proceeding 30524. [1]
- Public record
The AUC oral hearing is scheduled to begin. [1]
- Proponent projection
The proponent targets initial operation, subject to approvals and construction. [6]
What we still don't know
Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.
- The AUC has not issued a final decision on the proposed power plant.
- Municipal development permits for the data halls and related site construction were not confirmed in the reviewed public record.
- How Rocky View County's new discretionary permit framework will affect Beacon's later development-permit applications remains unresolved.
- A final investment decision, committed customers, financing structure and binding construction schedule were not found in the reviewed sources.
- The reviewed records do not reconcile the 946-acre municipal planning area with the 627.2-acre data-centre campus described in the federal filing.
- The reviewed records do not reconcile the construction employment estimates of more than 1,500 and up to 4,500 workers.
- Final water-service agreements, available system capacity, wastewater routing and phase-level demand have not been published.
- The filing describes carbon-capture readiness and other future mitigation options, but no capture facility, capture rate or operating commitment is established.
- Final gas-supply infrastructure, grid interconnection arrangements and any export of surplus generation remain unresolved.
Source record
Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.
- Beacon AI Centers Indus Project thermal power plant
Alberta Utilities Commission · Regulator · Updated through July 2026
- Beacon AI Hub Area Structure Plan
Rocky View County · Municipal record · Updated through July 2026
- Beacon AI Hub Area Structure Plan
Rocky View County · Municipal record · 2025-06-17
- Council Decisions: July 21, 2026
Rocky View County · Municipal record · 2026-07-21
- Emerging Sector Strategy
Rocky View County · Municipal record · Updated through July 2026
- Indus Data Center Hub Initial Project Description summary
Impact Assessment Agency of Canada · Federal filing · 2025-12-29
- Indus data centre frequently asked questions
Beacon Data Centers · Company disclosure · 2026-02
- Beacon Indus Data Center Hub
Government of Alberta Major Projects · Government database · Accessed 2026-07-28
- Beacon commits to an initial 4.5 GW Alberta portfolio
Beacon AI Centers / Business Wire · Company disclosure · 2025-05-15
- Calgary firm eyes $10B AI data centre building blitz
The Logic · News reporting · 2025-05-15