Verified project profile
Bitdeer Fox Creek
Bitdeer is constructing a 101.133 MW natural-gas power plant and an approximately 100 MW computing facility near Fox Creek. Its latest infrastructure table lists cryptocurrency as the planned use, while saying the data centre design is being developed to accommodate both AI data centre and cryptocurrency workloads.
Project facts
Core scale, approval, employment, and schedule information, labelled by the type of evidence available.
Computing capacity
Approximately 100 MWCurrent planned use is cryptocurrency; the design is intended to retain future AI/HPC capability.
Sources [1], [2]Power plant
101.133 MW natural gasThe AUC transferred the existing approval to Bitdeer in 2025.
Sources [3]Project status
Under constructionBitdeer held a groundbreaking in June 2026; Alberta Major Projects also lists the project as under construction.
Sources [1], [4]Latest energization target
Fourth quarter of 2027The August 2026 update replaced the earlier second-quarter 2027 target.
Sources [2]Site area
7.7 hectares (19 acres)Sources [1]Employment estimate
300 construction; 30 permanentCompany projections, not binding local-employment commitments.
Sources [1]Energy and emissions
The data centre is intended to receive power directly from a new natural-gas plant. The plant can also connect to Alberta's grid, and Bitdeer says compute could be curtailed so electricity can be exported during grid stress.
Purpose-specific generation
101.133 MWA flexible natural-gas plant approved by the AUC and now under construction.
Sources [3], [1]Computing capacity
Approximately 100 MWA facility-capacity claim, not measured operating demand.
Sources [1]Grid interconnection
99 MW approvedBitdeer says the plant can export to the grid when computing is curtailed. The reviewed sources do not promise a fixed amount or frequency of grid support.
Sources [1]Primary fuel
Natural gasBitdeer says it plans carbon-capture-and-use equipment, but ADCW did not find a final design, capture rate, operating commitment or verified emissions reduction.
Sources [1]Water
Bitdeer describes closed-loop dry cooling and says no nearby surface-water withdrawal is planned. The reviewed sources do not publish other construction, domestic or process-water volumes. [1]
Cooling
Closed-loopClosed-loop coolingCooling fluid circulates repeatedly through a contained loop instead of being routinely discharged after one pass.That describes the loop, not the whole site's water use. A separate heat-rejection system can still use water, and filling, maintenance, and leaks also matter.Learn more → dry coolingDry coolingDry cooling releases heat to the air without relying on water evaporation for that heat rejection.Fans and other equipment still use electricity and can produce sound. Check whether the design also uses wet or water-assisted equipment during hot weather.Learn more → proposedThe company says the system will not withdraw water from nearby bodies of water.
Sources [1]Other water needs
Not quantifiedNo comparable daily figure for construction, domestic use, fire protection or other site needs was found.
Sources [1]Noise
Bitdeer says preliminary work is being used to design for Alberta's nighttime limits and promises monitoring after operations begin. It has not published the receptor predictions or monitoring results.
Preliminary noise work
Receptor values not publishedBitdeer says preliminary studies are being used to design the facility to meet applicable Alberta nighttime noise limits. The published update does not provide the assessed receptors, predicted levels, or a complete mitigation schedule.
Sources [1]Operating monitoring
Promised after commissioningThe company says active monitoring will occur once the facility operates. No measured operating results exist yet because construction is still underway.
Sources [1]Indigenous context
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. This section brings together the public record on treaty geography, Indigenous ownership, consultation, and community concerns. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Approval and public process
The underlying power project was approved before Bitdeer acquired it, and the approval was transferred to Bitdeer in 2025. Construction is now underway, but environmental compliance and final data centre design work continue.
Power-plant approval
Approval transferred to BitdeerAUC Approval 29843-D02-2025 authorizes the 101.133 MW Opal Power Plant under Bitdeer's project company.
Sources [3]Environmental approval
EPEA industrial approval reportedBitdeer reports that the project holds an industrial approval. ADCW has not yet linked the complete approval record in this profile.
Sources [1]Current work
Power construction and data centre designThe latest company update says the design is being developed for both AIDC and cryptocurrency use.
Sources [2]Timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
- Public record
The AUC issued the original approval for the Opal Power Plant. [3]
- Proponent statement
Bitdeer announced acquisition of the licensed and permitted site. [1]
- Public record
The AUC transferred the 101.133 MW approval to Bitdeer's project company. [3]
- Proponent statement
Bitdeer held a groundbreaking and described the project as entering construction. [1]
- Proponent statement
Bitdeer moved its expected energization from Q2 to Q4 2027 and listed cryptocurrency as the planned use. [2]
- Proponent projection
Latest company target for energization. [2]
What we still don't know
Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.
- The final split between cryptocurrency, AI/HPC and other computing workloads at commissioning.
- The final data centre design, equipment count and measured operating demand.
- Project-specific greenhouse-gas, NOx and other emissions totals for the current design.
- The design, capture rate and operating commitment for the proposed carbon-capture-and-use system.
- Other water sources and volumes beyond the no-surface-water-withdrawal cooling claim.
- The complete EPEA approval, monitoring requirements and public compliance record.
- The frequency and quantity of possible electricity exports to the Alberta grid.
- A detailed project-specific Indigenous consultation record.
Source record
Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.
- Bitdeer breaks ground on Fox Creek facility
Bitdeer Technologies Group · Company disclosure · 2026-06-02
- Second-quarter 2026 results and infrastructure summary
Bitdeer Technologies Group · Company disclosure · 2026-08-10
- Power Plant Approval 29843-D02-2025
Alberta Utilities Commission · Regulator · 2025
- Bitdeer Crypto Mining Facility - Fox Creek
Government of Alberta Major Projects · Government database · Accessed 2026-08-21
- Treaty Boundary dataset
Government of Canada Open Government Portal · Government database · Modified 2026-06-29