Verified project profile
Armada Nowlit Data Centre Southeast of Clive
Armada Nowlit Energy Ltd. seeks rezoning on behalf of landowner Arkham Estates Corporation and Iceline Energy Inc. for an approximately 19.8 MW modular data-processing facility and natural-gas power plant at 40205 Range Road 243, southeast of Clive. The submitted package calls the data buildings miner containers, and company materials market digital-asset and AI computing, providing direct evidence of mining-oriented infrastructure without identifying a customer, installed hardware, specific cryptocurrency, or workload split. Lacombe County must decide the rezoning before a development-permit application can be made. The package says an AUC application is under review, but ADCW found no active Clive application.
Project facts
Core scale, approval, employment, and schedule information, labelled by the type of evidence available.
Proposed generation
Approximately 19.8 MWNine proposed 2.2 MW MWM TCG3020-series natural-gas generator sets, subject to final equipment selection. This is gross installed generation capacity, not a verified compute load.
Sources [2], [4]Data-processing buildings
Nine miner containersThe revised July 20, 2026 air-dispersion model labels the nine data buildings as miner containers MC1 to MC9. The package does not identify a customer, installed computing hardware, a specific cryptocurrency, or the share of capacity intended for mining.
Sources [2]Workload evidence
Digital-asset mining and AI marketedArmada Nowlit says its data centres support digital-asset and AI computing, and Nowlit markets ASIC and GPU infrastructure, blockchain, and mining services. Together with the miner-container description, this is direct evidence of mining-oriented infrastructure, but it does not confirm a specific coin or workload split at Clive.
Sources [2], [5], [6], [9]Rezoning area
4.40 acresThe application seeks to redesignate 4.40 acres of SE-16-40-24 W4M from Agricultural to Heavy Industrial. The package describes a 4.28-acre facility area and a 0.12-acre access area, leaving approximately 155.60 acres agricultural.
Sources [2]Construction period
Approximately one monthThe developer targets a March 2027 start and April 2027 completion, subject to approvals. The traffic assessment estimates 250–450 loaded truck events, or 500–900 one-way heavy-vehicle movements, with no night hauling proposed.
Sources [2]On-site workforce
Proponent documents conflictThe presentation projects 20–50 temporary construction jobs and 10–20 ongoing operations and service roles. The submitted traffic assessment instead assumes about 10 people on site on a typical construction day, no more than 15 at peak, and a normally unstaffed operating facility with one to three maintenance or service visits per month.
Sources [2]Clive investment
Approximately US$2 million claimedThe developer's presentation describes private infrastructure investment at Clive. ADCW did not independently verify the estimate, and it should not be confused with broader company-wide investment claims.
Sources [2]Foreign investment record
Hong Kong new-business notificationThe federal Investment Canada Act index records an April 2025 new-business notification by Armada Nowlit HK Limited, Central, Hong Kong SAR, China, associated with Armada Nowlit Power Ltd., Armada Nowlit Energy Ltd., and Armada Nowlit Canada Holding Limited. The index lists the ultimate controller's country of origin as Hong Kong SAR, China. It does not disclose an ownership percentage, investment amount, Chinese state ownership, or ownership of the Clive land.
Sources [10]Target operation
April–May 2027A developer schedule subject to engineering, approvals, and construction. It is not a regulatory deadline or confirmed in-service date.
Sources [2], [4]Energy and emissions
The current concept pairs nine natural-gas generator sets with nine co-located miner containers. The developer proposes to consume all electricity on site and not export power to the Alberta grid.
On-site gas generation
Nine × 2.2 MWThe current design basis uses nine enclosed 2.2 MW MWM TCG3020-series generator sets for approximately 19.8 MW gross capacity. Final equipment remains subject to design and procurement.
Sources [2], [4]Grid export
None proposedThe developer says all electricity would be consumed by the co-located data-processing equipment, with no export to the Alberta Interconnected Electric System.
Sources [2], [4]Natural-gas supply
Existing distribution tie-in proposedThe developer proposes a pipeline tie-in to existing gas distribution infrastructure. The supplier, route, capacity, connection design, and approvals remain unconfirmed.
Sources [4]Emissions controls
Selective catalytic reduction proposedThe current concept includes SCR systems. Final equipment, permit limits, monitoring, and operating conditions are not confirmed in the reviewed record.
Sources [2], [4]Short-term nitrogen dioxide
Below Alberta air-quality objective in modelThe revised model predicts a maximum one-hour ground-level concentration of 183.7 µg/m³, including estimated background and nearby sources, compared with Alberta's 300 µg/m³ objective. Nitrogen dioxide comes from burning fuel and can increase the risk of breathing problems. This is a prediction, not measured emissions or a regulatory finding.
Sources [2], [11]AUC status conflict
No active Clive application identifiedThe Council presentation says an AUC application is submitted and under review. The AUC's current application list identifies Armada Nowlit's Proceeding 30983 for a separate 4.88 MW Red Deer County facility, not Clive. Proceedings 30385, 30476, and 30709 are tied to Gayford in Rocky View County and are now tracked separately.
Sources [2], [7]Annual greenhouse-gas emissions
Not foundThe developer publishes local air-dispersion results but not a project-specific annual CO₂e estimate in the sources reviewed by ADCW.
Sources [2], [4]Water
The developer proposes sealed-loop liquid cooling with dry coolers, a roughly 1,500 L service-water tank, and a separate wastewater holding tank. Wastewater would be removed for off-site servicing with no discharge to land. Earlier application materials describe an initial 250–300 L water-glycol fill per unit and minor trucked top-ups, but do not define the unit or quantify annual water use. No municipal water connection or groundwater well is proposed. Tank capacity is not projected consumption. [2], [4]
Cooling system
Closed-loopClosed-loop coolingCooling fluid circulates repeatedly through a contained loop instead of being routinely discharged after one pass.That describes the loop, not the whole site's water use. A separate heat-rejection system can still use water, and filling, maintenance, and leaks also matter.Learn more → dry coolingDry coolingDry cooling releases heat to the air without relying on water evaporation for that heat rejection.Fans and other equipment still use electricity and can produce sound. Check whether the design also uses wet or water-assisted equipment during hot weather.Learn more → proposedThe developer proposes a sealed water-glycol loop with dry coolers that recirculates cooling fluid. Final equipment and operating performance are not independently verified.
Sources [2], [4]Initial coolant fill
250–300 L per unitThe developer says the initial water-glycol fill would be trucked to site. The package does not define the unit clearly enough to calculate a reliable project total.
Sources [2], [4]Municipal water connection
Not proposedThe developer says the current design would not connect to municipal water.
Sources [2], [4]Groundwater well
Not proposedThe developer says the current design would not use an on-site groundwater well.
Sources [2], [4]Routine top-up demand
Minor trucked top-ups claimedThe package describes occasional maintenance top-ups but does not quantify their expected frequency, annual volume, leakage, or replacement demand.
Sources [2]Service water and wastewater
Tank and off-site servicing proposedThe developer describes a roughly 1,500 L service-water tank and separate holding tank. It says wastewater would be removed off site with no dischargeWithdrawal, consumption, and dischargeWithdrawal is water taken from a source. Consumption is the portion not returned to the same water system. Discharge is water released after use or treatment.These are different quantities. Check which one a water figure describes before comparing projects.Learn more → to land. Tank capacity is not annual water use; a complete operating water balance and final approvals remain unpublished.
Sources [4]Noise
Project-specific noise evidence is shown when it is available. A predicted sound level is not a measurement from an operating facility.
Sound at nearby communities
36.0 dBA predicted at closest assessed homeThe developer's current page reports a 36.0 dBA modelledModelled versus measuredA modelled result is a prediction based on inputs and assumptions. A measured result comes from observations or instruments under particular conditions.A prediction is not verified operating performance. Check the location, period, operating scenario, and what the reported number actually represents.Learn more → nighttime total at the closest assessed residence, about 970 m north, against a stated 40 dBA limit. The earlier application-case assessment reports 35.3–35.9 dBA across receptors with assumed ambient sound; its cumulative case reports 35.4–36.2 dBA. These are different model summaries, not operating measurements. The consultant identified possible low-frequency tonal characteristics but concluded they were unlikely to be an issue because predicted project levels excluding ambient sound were 30 dBA or lower.
Sources [4], [2]Indigenous context
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. This section brings together the public record on treaty geography, Indigenous ownership, consultation, and community concerns. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty geography
Treaty 6 territoryThe federal historical treaty-boundary dataset places the project area within Treaty 6. This is geographic context, not evidence of project-specific consultation.
Sources [12]Project-specific consultation
Not foundThe reviewed public sources do not identify potentially affected First Nations or Métis communities, engagement completed, concerns raised, or accommodation measures for the Clive proposal.
Sources [4], [2]Approval and public process
Armada Nowlit Energy Ltd., on behalf of landowner Arkham Estates Corporation and Iceline Energy Inc., seeks to redesignate 4.40 acres of SE-16-40-24 W4M from Agricultural to Heavy Industrial. The County says a development-permit application can follow only if rezoning succeeds; the data processing centre would be a discretionary use at that stage. No municipal approval is confirmed. The developer meeting is September 30, 2026, with a survey scheduled for October 1–15, 2026; separate County engagement and a formal hearing would follow the County process. December 10, 2026 remains the developer's unconfirmed hearing estimate.
Power-plant regulator
Alberta Utilities CommissionThe AUC reviews power generation, transmission, and grid connections. Lacombe County says the AUC is the primary approval authority for a natural-gas power plant.
Sources [8]Rezoning before permit
4.40 acres to Heavy IndustrialLacombe County says Armada Nowlit Energy Ltd. seeks redesignation on behalf of landowner Arkham Estates Corporation and Iceline Energy Inc. The data processing centre would be a discretionary use in a later development-permit application, possible only after successful rezoning. Rezoning itself would not authorize construction.
Sources [3]AUC application claim
Not verified for CliveThe developer's presentation says an AUC application is under review. ADCW did not identify a corresponding active Clive proceeding. Proceedings 30385, 30476, and 30709 concern the separate Gayford facility.
Sources [2], [7]AEPA approval claim
Draft approval claimed; instrument not identifiedThe presentation lists Alberta Environment and Protected Areas at 'Draft Approval' but provides no approval number, authorization type, conditions, or copy. ADCW did not identify a project-specific approval in the reviewed official record.
Sources [2], [8]Who pays for cleanup?
C$1.96 million estimated; no security confirmedThe developer estimates cleanup at about C$1.96 million and proposes arranging a bond or similar guarantee later. The package does not show that this money is secured, who could access it if the company failed to clean up, or whether the estimate would keep pace with rising costs over the project's life.
Sources [2]Developer meeting
September 30, 2026, 6–8 p.m.Tees Community Hall. Lacombe County confirms this developer-hosted public information meeting.
Sources [1]Developer feedback survey
October 1–15, 2026The developer says its survey opens October 1 and closes October 15, 2026, at 11:59 p.m. This is separate from the County's required public hearing.
Sources [4]Separate County engagement
Late 2026 or early 2027County-led public engagement is separate from the developer meeting and from a formal rezoning hearing. A specific date has not been announced.
Sources [1]Estimated public hearing
December 10, 2026The date appears in the developer's proposed schedule. It is not a final hearing notice or evidence that Council has advanced the application.
Sources [2]Timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
- Public record
The federal Investment Canada Act index records a new-business notification by Armada Nowlit HK Limited, associated with Armada Nowlit Power Ltd., Armada Nowlit Energy Ltd., and Armada Nowlit Canada Holding Limited. [10]
- Proponent statement
The revised air-dispersion model described the nine data buildings as miner containers MC1 to MC9. [2]
- Public record
The County confirms that no municipal approvals have been granted and announces public engagement opportunities. [1]
- Public record
Confirmed developer meeting, 6–8 p.m., Tees Community Hall. [3]
- Proponent statement
Developer feedback survey scheduled following the public meeting; this is separate from County engagement. [4]
- Public record
Separate County-led engagement is planned; no specific date has been announced. [1]
- Proponent projection
The developer's schedule estimates a municipal public hearing. This is not a final hearing notice. [2]
What we still don't know
Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.
- Whether Armada Nowlit will submit a Clive-specific AUC application. ADCW could not verify the package's claim that one is currently under review.
- Whether Lacombe County will approve the requested redesignation and any later development permit, road-use agreement, or other municipal authorization.
- What the presentation's 'Draft Approval' from Alberta Environment and Protected Areas refers to, including the authorization type, number, conditions, and current status.
- The separate data-centre electrical load, customer, installed computing hardware, specific cryptocurrency, and expected split between digital-asset mining and AI workloads.
- Why the presentation projects 10–20 ongoing roles while the traffic assessment describes a normally unstaffed facility with one to three maintenance or service visits per month.
- The final natural-gas supplier, connection route, contracted capacity, and required pipeline or utility approvals are not disclosed.
- Routine cooling-water top-up, total coolant inventory, wastewater volume, off-site servicing arrangements, and emergency spill-management volumes are not quantified.
- A project-specific annual greenhouse-gas estimate, final emissions limits, and monitoring requirements were not found.
- Whether cleanup security will be required before construction, who would hold or enforce it, and how the amount would be adjusted as costs rise.
- Final equipment procurement, customer commitments, project financing, and a binding construction schedule are not publicly confirmed.
- Project-specific Indigenous consultation participants, concerns, outcomes, and accommodation measures were not found.
- The final drainage design, emergency-response arrangements, and cumulative-effects assessment remain unresolved in the reviewed public record.
Source record
Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.
- Lacombe County expands public information as Natural Gas Power Plant/Data Centre proposal enters review process
Lacombe County · Municipal record · 2026-08-27
- August 27, 2026 Council agenda: Armada Nowlit Energy Ltd. Clive Facility
Lacombe County · Municipal record · Meeting scheduled 2026-08-27
- Armada Nowlit Energy Ltd. | Proposed Clive Facility
Lacombe County · Municipal record · Accessed 2026-09-29
- Proposed Clive Facility
Nowlit Solutions Corp. · Company disclosure · Accessed 2026-09-29
- Armada Nowlit corporate site
Armada Nowlit · Company disclosure · Accessed 2026-08-25
- Infrastructure and computing services
Nowlit · Company disclosure · Accessed 2026-08-25
- Current applications
Alberta Utilities Commission · Regulator · Accessed 2026-08-25
- Data Centre & Natural Gas Power Generation Projects FAQs
Lacombe County · Municipal record · Accessed 2026-09-27
- Data Center, Clive
Government of Alberta Major Projects · Government database · Accessed 2026-08-25
- Investment Canada Act: index of decisions and notifications
Innovation, Science and Economic Development Canada · Government database · April 2025 notification; accessed 2026-08-25
- Air indicators – Nitrogen dioxide
Government of Alberta · Government database · Updated February 2026
- Treaty Boundary dataset
Government of Canada Open Government Portal · Government database · Modified 2026-06-29