Verified project profile
Goldfinch Technology Park Data Centre
Goldfinch is Diode Ventures' proposed data centre park west of Carseland. Wheatland County's final consolidated plan records adoption of the Diode area concept plan on August 11, 2026, not a project-specific development permit. AESO's 950 MW grid request remains at Stage 2 with dates under review. The future operator, workload, final cooling design and water demand are not publicly confirmed.
Project facts
Core scale, approval, employment, and schedule information, labelled by the type of evidence available.
Planning area
Approximately 576 acres (233 hectares)The June notice gives 576.34 acres. The marker represents the planning area, not a surveyed building location.
Sources [2]Developer
Diode VenturesDiode describes itself as a Black & Veatch subsidiary that prepares the site for a future end user.
Sources [3]Future operator and workload
Not confirmedSources [3]Planning decision
August 11, 2026The final consolidated Goldfinch plan records the Diode area concept plan as adopted under Bylaw 2025-32.
Sources [1]Planning category
Medium IndustrialThe adopted ASP says this category may include technology centres and associated power generation or energy-conversion systems. It is a planning framework, not approval of a final on-site power design.
Sources [1]Construction or operation date
Not confirmedSources [3], [4]Energy and emissions
The grid request establishes a proposed connection scale, not a commissioned facility or a guaranteed supply date.
AESO request
P3102: 650 MW + 300 MWGoldfinch Technology Park MPC Load, Stage 2. Both DTS stages have in-service dates under review in the August 2026 list.
Sources [4]Final supply and grid upgrades
Not confirmedDiode says AESO studies will determine needed upgrades. A queue entry does not grant construction approval or guarantee a connection.
Sources [3], [5]Backup generationBackup generationBackup generators provide electricity when the normal supply is unavailable. They may also run for testing or maintenance.Installed capacity does not establish continuous operation, annual fuel use, or emissions. Operating hours and permit conditions are separate evidence.Learn more →
Equipment and fuel not confirmedNo final generator inventory, fuel plan or operating hours were found.
Sources [3], [2]Annual electricity use and emissions
Not quantifiedNo project-specific MWh/year or tonnes CO₂e/year estimate was identified. Connection capacity alone cannot establish either.
Sources [4], [3]Water
Cooling selection and the full water balance remain unresolved. A commitment not to use local aquifer water for cooling does not establish zero site water use. [2], [3]
Cooling technology
Final selection pendingDiode says the cooling strategy will be determined at the development-permit stage.
Sources [3]Local aquifer cooling water
Not proposedWSP's June submission excludes local aquifer process water for cooling, while identifying domestic use and stored fire-protection water.
Sources [2]Water demand and approvals
Not confirmedNo final daily or annual withdrawalWithdrawal, consumption, and dischargeWithdrawal is water taken from a source. Consumption is the portion not returned to the same water system. Discharge is water released after use or treatment.These are different quantities. Check which one a water figure describes before comparing projects.Learn more →, consumption or wastewater volume, supply allocation or project-specific water authorization was identified in the reviewed sources.
Sources [2], [3]Water supply for Goldfinch
Not confirmedThe industrial park already has a pipeline carrying untreated water to CGC, a drywall manufacturer. The County has not confirmed that Diode's data centre will use it.
Sources [6]Rainwater and snowmelt
Storage proposed; final drainage design unresolvedWSP proposes temporarily holding rainwater and snowmelt on site to meet irrigation-season restrictions on releasing runoff. The final design for storing and managing this water is not yet confirmed.
Sources [2]Noise
Noise studies are a future permit requirement, not evidence of demonstrated operating performance. The reviewed sources contain no numerical receptor results.
Noise-impact assessment
Required at each development-permit stageWSP's June submission describes this requirement. Numerical receptor tables were not found in the reviewed public package.
Sources [2]Mitigation
Proposed, not verifiedDiode lists berms, landscaping, sound barriers, generator enclosures and mufflers as possible measures. Final specifications and measured performance are not available.
Sources [3]Indigenous context
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. This section brings together the public record on treaty geography, Indigenous ownership, consultation, and community concerns. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty geography
Treaty 7 territoryGeographic context only. It does not establish consultation, consent or a community's position on this proposal.
Sources [7]Project-specific consultation
Not established in reviewed sourcesParticipants, concerns, outcomes and accommodation measures were not identified.
Sources [2], [3]Approval and public process
Land-use planning, a development permit and construction are separate steps. Wheatland County's final consolidated Goldfinch plan records the Diode area concept plan as adopted under Bylaw 2025-32 on August 11, 2026. It also places technology centres, including associated power generation or energy-conversion systems, within the Medium Industrial policy category. The County archive label and PDF filename say 2026-32, but that number does not appear inside the final plan.
Final planning instrument
Goldfinch ASP and Diode ACP adoptedThe final consolidated plan records the Diode area concept plan as adopted under Bylaw 2025-32 on August 11, 2026. The County archive label and PDF filename call the document Bylaw 2026-32, but the plan itself uses 2025-32. ADCW follows the number printed inside the final plan.
Sources [1]Next permit stage
Discretionary development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more →The June submission identifies a later discretionary permit review. ADCW has not verified an issued project-specific development permit.
Sources [2], [3]Detailed design
Still to be submittedDiode identifies site layout, buildings, noise, servicing and construction timing as later permit details.
Sources [3]Infrastructure cost framework
Off-site levies and development agreementsThe adopted ASP says developers will fund utility and road improvements that benefit future development. Front-ending, cost recovery and cost-sharing may apply. No Goldfinch-specific amount or agreement is disclosed.
Sources [1]Timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
- Public record
Application date recorded by AESO for P3102. [4]
- Public record
County notice schedules a July 7 public hearing on the planning proposal. [2]
- Public record
Wheatland County adopted the Diode Ventures Data Centre Area Concept Plan within the final consolidated Goldfinch Industrial Area Structure Plan. This planning instrument is not a project-specific development permit. [1]
What we still don't know
Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.
- An issued development permit, approved building layout, conditions and construction start have not been verified.
- The future operator, tenants, workload and contracted compute capacity remain undisclosed.
- Final grid connection dates, network upgrades, cost allocation and power-supply contracts are not confirmed.
- The final cooling design, water source, allocation, annual demand and wastewater arrangements remain unresolved.
- No numerical noise receptor assessment or final generator and cooling-equipment specifications were found.
- Project-specific annual electricity consumption, greenhouse-gas emissions and backup-generator air emissions are not quantified.
- The June public package lists supporting technical reports but does not reproduce them all. Listing a report does not establish its findings.
- Project-specific Indigenous consultation outcomes, enforceable cleanup security and a binding operating schedule were not found.
Source record
Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.
- Goldfinch Industrial Area Structure Plan, final consolidated plan
Wheatland County · Municipal record · Adopted 2026-08-11; accessed 2026-09-09
- PL2025-005: June public-hearing notice, WSP submission letter and conceptual maps
Wheatland County / WSP for Diode Ventures · Municipal record · 2026-06-03; submission letter 2026-06-01
- Goldfinch project updates
Diode Ventures · Company disclosure · Accessed 2026-08-30
- August 2026 Connection Project List: P3102, row 173
Alberta Electric System Operator · Regulator · 2026-08-05
- Connection Project Reporting
Alberta Electric System Operator · Regulator · Updated 2026-08-05; accessed 2026-08-30
- Goldfinch Raw Water Line
Wheatland County · Municipal record · Accessed 2026-08-30
- Treaty Boundary dataset
Government of Canada Open Government Portal · Government database · Modified 2026-06-29