Verified project profile

Kakwa Data Processing Centre

New West Data Acquisition Corp. proposes multiple cryptocurrency data-processing pods at an existing industrial lease site in the Kakwa area. The AUC approved an 8.40 MW isolated gas plant in February 2026, and a Crown disposition for cryptocurrency activity took effect in June 2026. Greenview's September 9, 2026 agenda recommends approval of D26-087, but the reviewed package is not an issued municipal permit or meeting decision.

New West Data Acquisition Corp.
How to read this profilePublic recordProponent statementProponent projectionProponent projectionA forecast, target, estimate, or promised future outcome from the company proposing the project.The label identifies whose projection it is. It does not turn a future claim into an independently verified result or an enforceable approval condition.Learn more →ADCW context

Project facts

Core scale, approval, employment, and schedule information, labelled by the type of evidence available.

Public record

Municipal file

D26-087

Discretionary-use development-permit application scheduled for the September 9, 2026 Municipal Planning Commission meeting.

Sources [1]
Public record

Proposed municipal limit

Up to 9.9 MW

The recommended motion applies this ceiling to the data-processing centre. It is not a measured load or evidence of approval.

Sources [1]
Public record

AUC proceedingAUC proceedingA proceeding is the Alberta Utilities Commission's formal record for reviewing an application, including evidence, submissions, and a decision when issued.A proceeding number helps locate the record. The existence of a proceeding does not mean the application has been approved.Learn more →

30521

Application 30521-A001 resulted in Decision 30521-D01-2026 and Approval 30521-D02-2026.

Sources [2], [3], [4]
Public record

Workload

Cryptocurrency mining

Greenview's agenda and Crown disposition identify the proposed activity as cryptocurrency data processing.

Sources [1]
Public record

Subject property

Approx. 1.32 ha

The municipal report describes the Crown-land lease site as approximately 3.26 acres. The survey identifies a smaller 0.248-hectare cryptocurrency activity area.

Sources [1]
Public record

Crown disposition

DLO260092

Effective June 15, 2026 and expiring January 22, 2044, or earlier with the primary disposition.

Sources [1]

Energy and emissions

The 9.9 MW municipal limit and the 8.40 MW AUC-approved power plant describe different things. ADCW reports the proposed data-centre ceiling and purpose-specific generation separately and does not add them together.

Important distinction: The approved power plant is isolated from the Alberta grid. Approval of the power plant does not establish that the data centre received its municipal permit, completed construction, or began operating.
Public record

Approved generation

8.40 MW

Five Caterpillar G3520 natural-gas reciprocating engines.

Sources [3], [4]
Public record

Grid relationship

Isolated and off-gridNon-grid-connectedThe facility has no electrical connection to Alberta's interconnected grid and relies on supply available to the site.It does not directly draw from or send electricity to that grid. Power-plant approvals and local impacts can still matter.Learn more →

The AUC application says the plant would not connect to the Alberta Interconnected Electric System. The Crown disposition also requires standalone power.

Sources [2], [1]
Public record

AUC construction deadline

June 30, 2026

The approval required completion by this date unless otherwise authorized. The date passing does not prove construction was completed.

Sources [4]
Public record

Environmental approval dependency

Status not confirmed

The AUC said construction could not begin until the Environmental Protection and Enhancement Act industrial application was approved. The reviewed records do not confirm the later decision.

Sources [3]
Public record

AER facility licence

F53063 amendment cited

Greenview staff list an Alberta Energy Regulator facility licence amendment among the supporting records. The amendment itself was not included in the four documents reviewed by ADCW.

Sources [1]

Water

The reviewed records do not quantify data-centre water demand or identify a cooling system. Recommended municipal conditions address runoff, groundwater, and watercourses but are not evidence of routine water use. [1]

ADCW context

Cooling and routine water demand

Not publicly quantified

The reviewed records do not identify a cooling design or quantify operational water withdrawalWithdrawal, consumption, and dischargeWithdrawal is water taken from a source. Consumption is the portion not returned to the same water system. Discharge is water released after use or treatment.These are different quantities. Check which one a water figure describes before comparing projects.Learn more →, consumption, or discharge for the data centre.

Sources [1]
Public record

Recommended municipal safeguards

Runoff and watercourse protections

If adopted, the recommended permit conditions would require runoff not to exceed pre-development flows and would restrict impacts to groundwater, drainage, and watercourses. These are recommended conditions, not a verified issued permit.

Sources [1]

Noise

Greenview staff report a highest modelled cumulative level of 39.7 dBA at the most affected receptor, below the applicable 40.0 dBA limit. The result comes from an applicant assessment and is not an operating measurement.

Proponent projection

Highest modelledModelled versus measuredA modelled result is a prediction based on inputs and assumptions. A measured result comes from observations or instruments under particular conditions.A prediction is not verified operating performance. Check the location, period, operating scenario, and what the reported number actually represents.Learn more → cumulative sound

39.7 dBA

Greenview staff report 39.7 dBA at the most affected receptor against a 40.0 dBA permissible level. This is applicant modelling, not an operating measurement.

Sources [1]
Public record

Nearby residences

None known within 1.5 km

The municipal report and survey state that no residence was known within 1.5 kilometres. This does not establish measured operating sound.

Sources [1]

Indigenous context

Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. This section brings together the public record on treaty geography, Indigenous ownership, consultation, and community concerns. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.

Proponent statement

Consultation geography

Crown land within the consultation radii

The applicant reported no First Nations reserve or Métis Settlement within the consultation radii. That statement does not establish whether Indigenous rights or interests may be affected.

Sources [2], [3]
Public record

Consultation path

No Crown consultation directed for the AUC filing

The applicant said its land agent advised that the filing did not trigger Crown consultation notice. The AUC recorded that the applicant would follow Alberta Energy Regulator direction for the separate Environmental Protection and Enhancement Act process. These records do not establish consultation, consent, or any community's position.

Sources [2], [3]

Approval and public process

The power plant approval, Crown disposition, Alberta Energy Regulator licence, environmental authorization, and municipal development permit are separate decisions. The municipal record reviewed by ADCW contains an approval recommendation, not the Commission's recorded vote or an issued permit.

Public record

Municipal status

Approval recommended, decision not reviewed

Greenview administration recommended approval at the September 9, 2026 meeting. An agenda recommendation is not the Municipal Planning Commission's decision.

Sources [1]
Public record

Land-use classification

Discretionary use

A Data Processing Centre is discretionary in the Crown Land District under Land Use Bylaw 25-1000.

Sources [1]
Public record

Post-decision notice

Minimum 21-day circulation

The agenda says an approved discretionary-use permit must be circulated for at least 21 days after the decision is issued.

Sources [1]
Public record

Provincial land authorization

DLO260092 issued

The disposition authorizes cryptocurrency-related commercial activity but requires compliance with all other applicable permits and approvals.

Sources [1]
Public record

Other permits

Still separate

The recommended municipal conditions require safety-code permits and a roadside development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more → before development begins.

Sources [1]

Timeline

Observed decisions and future dates are kept distinct; projected milestones may change.

  1. Public record

    New West Data Acquisition Corp. registers Application 30521-A001 for the 8.40 MW Kakwa Isolated Power Plant. [2][3]

  2. Public record

    The AUC approves construction and operation of the isolated natural-gas power plant, subject to its terms and other required authorizations. [3][4]

  3. Public record

    Crown disposition DLO260092 takes effect for overlapping rural commercial cryptocurrency activity. [1]

  4. Public record

    Greenview's Municipal Planning Commission agenda presents D26-087 with an administrative recommendation to approve the data-processing centre. The reviewed package does not record the Commission's decision. [1]

  5. Public record

    Crown disposition DLO260092 is scheduled to expire, unless it ends earlier with the primary disposition or changes under applicable law. [1]

What we still don't know

Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.

  • The reviewed agenda package does not establish whether the Municipal Planning Commission approved, refused, or tabled D26-087, or whether an issued permit became effective after notice and appeal.
  • The reviewed sources do not confirm whether the power plant met its June 30, 2026 construction deadline, received an extension, was completed, or entered service.
  • The Environmental Protection and Enhancement Act industrial-approval status is not confirmed in the reviewed records.
  • The number, design, operator, computing equipment, and operating status of the data-processing pods are not fully established.
  • The relationship between the proposed 9.9 MW municipal ceiling and the approved 8.40 MW generation capacity is not explained.
  • Cooling technology, routine water demand, wastewater, fire-protection water, fuel use, greenhouse-gas emissions, and measured operating noise are not publicly quantified in the reviewed records.
  • Treaty geography and project-specific Indigenous consultation outcomes or community positions are not established in the reviewed sources.

Source record

Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.

  1. Proceeding 30521: Rule 007 application for the Kakwa Isolated Power Plant

    New West Data Acquisition Corp. / Alberta Utilities Commission · Regulatory filing · 2025-12-22

  2. Decision 30521-D01-2026: 8.40-Megawatt Kakwa Isolated Power Plant

    Alberta Utilities Commission · Regulator · 2026-02-12

  3. Approval 30521-D02-2026: 8.40-Megawatt Kakwa Isolated Power Plant

    Alberta Utilities Commission · Regulator · 2026-02-12