Verified project profile
Mihta Askiy Data Centre
Mihta Askiy is a proposed 650 MW data centre and natural-gas power project at the former Carmon Creek industrial site northeast of Peace River. The project is 51 per cent owned by Woodland Cree First Nation. The federal government decided that a full federal impact assessment was not required, but that was not permission to build. The proposed power plant and substation are still under review by the Alberta Utilities Commission.
Project facts
Core scale, approval, employment and schedule information, labelled by the type of evidence available.
Ownership
51% Woodland Cree First NationSovereign Digital Infrastructure holds the remaining 49 per cent, according to the federal filing.
Sources [3]Initial data centre
400 MWTwo proposed 200 MW phases at the reused Carmon Creek site.
Sources [3]Full-build data centre
650 MWThe filing describes a later 250 MW expansion.
Sources [3]AUC proceeding
30787The active applications cover a 650 MW combined-cycle power plant and the Sunrise Substation.
Sources [1]Power-site footprint
About 20.6 hectaresThe filing describes reuse of the partially developed former Shell Carmon Creek site and says no additional power-plant clearing is planned.
Sources [3]Operations employment
About 40 full-time jobsA proponent estimate for the combined power plant and data centre. A construction workforce estimate was not found in the reviewed filing.
Sources [3]Expected operating life
30 yearsThe federal registry describes the proposed operating period.
Sources [2]Energy and emissions
The project would begin with approximately 400 MW of simple-cycle natural-gas generation and later expand to 650 MW in combined-cycle configuration.
Initial generation
Approximately 400 MWTwo natural-gas turbines would operate in simple-cycle configuration during the initial phase.
Sources [3]Full-build generation
650 MWA later steam turbine would convert the plant to combined cycle and support the expanded data centre.
Sources [3], [1]Grid connection
Two 240 kV transmission linesThe filing proposes connections between the project substation and the existing Wesley Creek Substation.
Sources [3]AUC facilities
Power plant and Sunrise SubstationProceeding 30787 covers the 650 MW combined-cycle facility and associated substation applications.
Sources [1]Annual GHG estimate
Not resolvedThe filing's annual totals do not align mathematically with its 400 MW capacity and stated 556.906 kg/MWh emissions intensity. An updated air-quality assessment was identified for the AUC process.
Sources [3]Water
The filing projects up to 5,000 cubic metres of daily water use for the initial phase and discusses earlier Carmon Creek infrastructure. Current licences, intake capacity and required upgrades remain unresolved. [3], [5]
Initial daily use
Up to 5,000 m³A proponent projection for the initial power and data-centre phase.
Sources [3]Historical planning volume
Up to 11,000 m³ per dayThe filing discusses water volumes associated with earlier Shell planning. This is not evidence that Mihta Askiy currently holds authorization to withdraw that amount.
Sources [3], [5]Proposed source
Peace RiverThe project expects to use or adapt infrastructure associated with the former Carmon Creek development.
Sources [3]Power-plant cooling
Evaporative cooling anticipatedThe combined-cycle steam condenser is expected to use evaporative cooling.
Sources [3]Data-centre cooling
Closed-loop system proposedThe filing distinguishes the data-centre cooling loop from the power plant's anticipated cooling system.
Sources [3]Infrastructure status
Capacity and upgrades unresolvedNorthern Sunrise County asked the proponent to confirm the water source, engage affected infrastructure owners and identify upgrades because earlier intake modifications were not completed.
Sources [5]Approval and public process
The federal decision means no further assessment under the federal Impact Assessment Act. It is not project approval and does not replace AUC, Water Act or other required authorizations.
Federal early decision
No further federal assessment requiredThe Impact Assessment Agency concluded that likely effects could be limited or addressed through other laws. The decision explicitly does not approve the project.
Sources [4]AUC review
Active proceedingProceeding 30787 reviews the proposed power plant and Sunrise Substation.
Sources [1]Other authorizations
Still requiredThe project remains subject to applicable federal and provincial permits, licences and approvals.
Sources [4], [2]Municipal concerns
Water, workforce and emergency planning raisedNorthern Sunrise County asked for clearer permit status, socioeconomic and housing information, emergency planning and infrastructure commitments.
Sources [5]Indigenous ownership
Majority First Nation-ownedWoodland Cree First Nation's ownership is a central project feature. The filing also identifies engagement with other Indigenous communities and regulators as an ongoing requirement.
Sources [3], [4]Timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
- ADCW context
Shell suspended the Carmon Creek development, leaving partially constructed industrial infrastructure later proposed for reuse. [3]
- Public record
Northern Sunrise County submitted comments on permits, water infrastructure, workforce planning and emergency services. [5]
- Public record
The Impact Assessment Agency issued its early decision that no further federal impact assessment was required. [4]
- Public record
The AUC opened public participation in Proceeding 30787 for the power plant and substation applications. [1]
- Proponent projection
The proponent targets initial 400 MW operation, subject to approvals and construction. [3]
- Proponent projection
The proponent targets combined-cycle conversion and expansion to 650 MW. [3]
What we still don't know
Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.
- The AUC has not issued a final decision on the proposed power plant and Sunrise Substation.
- A final investment decision, committed customers, financing structure and binding construction schedule were not found in the reviewed public record.
- The current status and transfer or reissuance requirements for permits associated with the former Carmon Creek project remain unresolved.
- The final Water Act licence, authorized withdrawal volume, intake capacity, infrastructure ownership and required upgrades were not established in the reviewed sources.
- The federal filing's annual greenhouse-gas table is internally inconsistent. A corrected project-specific annual estimate is needed.
- The filing estimates about 40 permanent jobs but does not provide a construction workforce estimate or binding local-employment commitments.
- Final transmission routing, interconnection terms and the balance between on-site consumption and grid exchange have not been published.
- The scope, governance and capacity of the proposed Woodland Cree language and cultural data component have not been published in detail.
- Municipal development approvals, emergency-service agreements, housing impacts, tax revenue and community-benefit commitments remain unresolved.
Source record
Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.
- Current applications (search Proceeding 30787)
Alberta Utilities Commission · Regulator · Accessed 2026-07-28
- Mihta Askiy Data Center Project registry
Impact Assessment Agency of Canada · Federal filing · Updated through July 2026
- Mihta Askiy Data Center Initial Project Description
Impact Assessment Agency of Canada · Federal filing · 2025
- Early decision with reasons
Impact Assessment Agency of Canada · Regulator · 2026-03-03
- Northern Sunrise County submission on the Initial Project Description
Northern Sunrise County · Municipal record · 2026-01-21
- Mihta Askiy project location data
Impact Assessment Agency of Canada · Federal filing · 2025
- Mihta Askiy Data Centre
Government of Alberta Major Projects · Government database · Accessed 2026-07-28