
Radiant Ridge Wetwin / Nordcon 1 Data Centre
An 860 ft² off-grid Bitcoin-mining proposal southwest of Wetaskiwin. The County conditionally approved D26/169 on August 27, 2026. The appeal outcome remains unverified.
Radiant Ridge proposes to use gas from an existing Norwegian Energy lease to power a data container. The municipal permit also covers a generator container and a separator building. Technical filings describe a 980 kW system, the April 22, 2026 handout gives 990 kW maximum station output, and the March 27, 2026 noise study modelled four 300 kW units. The record leaves the final generating capability unresolved.
Where it stands
Separate approval tracks, not a construction progress bar. Record last verified 2026-11-26.
The reviewed tribunal record includes party submissions on noise, the setback, and referral. A current participation deadline and the final outcome remain unverified. See the approval and participation record ↓
Power and emissionsCampus demand, electricity supply, and emissions evidence
Radiant Ridge proposes to run the Bitcoin-mining equipment on gas from the existing lease without a grid connection.
Important distinction: The filings give different figures for the gas power system. Final generating capability, the applicable provincial approval or exemption, and the mining equipment’s electricity demand remain unverified.
Gas power described in the project filings: 980 kW, 990 kW, and four 300 kW units. The April 17, 2026 desktop assessment, June 2026 biophysical assessment, and July 3, 2026 reclamation plan describe a 980 kW off-gridNon-grid-connectedThe facility has no electrical connection to Alberta's interconnected grid and relies on supply available to the site.It does not directly draw from or send electricity to that grid. Power-plant approvals and local impacts can still matter.Learn more → system. The April 22, 2026 handout lists 990 kW maximum station output and four gas generators. The March 27, 2026 noise study used four 300 kW units, whose individual ratings add to 1,200 kW. The documents do not explain how these figures relate or establish the load of the mining equipment. [3][4][2] ADCW context
Provincial authorization: Wetwin approval or exemption unverified. The April 22, 2026 handout said Radiant Ridge intended to apply to the Alberta Utilities Commission (AUC). The County bylaw calls for AUC approval before permit issuance where required, or demonstration of an applicable exemption. It notes that generation below 1 MW may qualify, subject to provincial requirements. The County points to its condition requiring applicable approvals before operation. The reviewed record does not establish the rating used to apply those rules. [4][7][1][6] Public record
What remains unresolved
Which generator ratings govern the project, and what provincial approval or exemption applies?
Water, cooling, and drainageSupply, demand, wastewater, and servicing
Radiant Ridge and the County say the facility would use no water. The project's filings describe cooling differently, and the County permit requires any necessary provincial water approvals before operation. [5][6][2][1]
Cooling and water use: Final design and water balance unverified. The March 27, 2026 study modelledModelled versus measuredA modelled result is a prediction based on inputs and assumptions. A measured result comes from observations or instruments under particular conditions.A prediction is not verified operating performance. Check the location, period, operating scenario, and what the reported number actually represents.Learn more → liquid-cooledLiquid coolingLiquid carries heat away from computing equipment, for example through cold plates at the chips.This describes how heat leaves the equipment. It does not identify how heat is ultimately released outside, or establish the site's water demand.Learn more → mining equipment. Radiant Ridge’s April 22, 2026 handout and November 5, 2026 submission describe air cooling. A liquid loop can release heat to the air. The amount needed to fill or replenish a system, any water authorizations, and the arrangements for handling fluids from gas production remain open. [2][4][5][1][6] ADCW context
What remains unresolved
What is the final cooling design, what water or fluids would it handle, and has anything been installed or commissioned?
Sound at nearby communitiesAssessment evidence, controls, and remaining questions
The consultant predicted sound at nearby dwellings. The County imposed separate limits at the development-site boundary and defended those conditions in the appeal.
Sound at nearby communities: 39.1 dBA predicted at night at the nearest dwelling. FDI Acoustics modelled a dwelling about 505 m away at 45.6 dBA by day and 39.1 dBA at night, against limits of 50 and 40 dBA respectively. That leaves a 0.9 dBA nighttime margin, with equipment on the southwest part of the pad and a south berm at least 4 m tall. No operating measurements were provided in the reviewed records. [2] Public record
County permit conditions under appeal: 4 m perimeter berm and boundary limits. The County identifies a reduction of the dwelling setback under section 9.20.3 and links it to its noise conditions. The permit sets 50 dBA at the property boundary during the day on weekdays and 40 dBA at night, on weekends, and on statutory holidays. Radiant Ridge asked to begin operation, measure at nearby dwellings, and add mitigation if necessary. The County defended its original conditions. [1][7][5][6] Public record
Land, wetlands, and wildlifeSite area and the available environmental record
Project and site: Wetwin / Nordcon 1. The County’s notice describes a data container, generator container, and separator building with a combined area of 860 ft². Technical reports identify Nordcon 1 on the Norwegian Energy lease, and Radiant Ridge’s November submission identifies the proposed use as Bitcoin mining. [1][3][5] Public record
Indigenous contextTreaty geography, engagement, and consultation evidence
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty 6 and Ermineskin Cree Nation: County says Ermineskin should have received a referral before approval. The County says the reserve is within the 1.6 km referral distance in its Municipal Development Plan. It found no record of completed referrals before the decision and says it sent Ermineskin notices of the decision. Ermineskin raised concerns about early participation through its official consultation channels. The County argues the appeal gives the Nation an opportunity to be heard. The tribunal’s findings on the process and the remedy remain unverified. [8][6][9] Public record
Approvals and participationSeparate decisions, public participation, and the recorded timeline
County development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more → D26/169 was conditionally approved on August 27, 2026 and is under appeal. The outcome and current work authorization remain unverified.
Land and Property Rights Tribunal: D26/169 appeal outcome unverified. The County’s November 19, 2026 rebuttal cites preliminary decision LPRT2026/MG0671 and responds to submissions by Radiant Ridge and other parties. Final permit conditions and current work authorization remain unresolved in the documents reviewed. [1][6] Public record
Recorded timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
2026-03-27. FDI Acoustics assessed the proposed equipment and modelled sound at nearby dwellings. [2] Public record
2026-04-22. Radiant Ridge’s handout described four gas generators and a maximum station output of 990 kW. [4] Proponent statement
2026-08-27. The County conditionally approved D26/169. Its September 9, 2026 notice restated the decision and permit conditions. [1] Public record
2026-11-19. The County defended the noise conditions and acknowledged that Ermineskin should have received a referral. [6] Public record
What remains unresolved
What did the tribunal decide, and which permit conditions now apply?
Company and commitmentsScale, projected benefits, and delivery commitments
Operating schedule: 24 hours a day proposed. The County permit allows continuous equipment operation subject to its conditions. Commissioning and operation remain unverified. [1] Public record
Project overview
Radiant Ridge proposes an 860 ft² off-grid Bitcoin-mining facility on a Norwegian Energy lease southwest of Wetaskiwin. The County conditionally approved D26/169 on August 27, 2026. The permit was appealed, and the outcome is unverified. The proposed gas power system is described as 980 kW in technical filings and 990 kW in the April 22, 2026 handout. The March 27, 2026 noise study modelled four 300 kW generators.
Unresolved questions are retained within each relevant topic above.
SourcesOriginal documents and publication details
Source record
Company disclosures establish what the company said, not independent verification of projected outcomes.
- D26/169 notice to adjacent landownersCounty of Wetaskiwin · Municipal record · 2026-09-09
- Wetwin noise impact assessment (selected pages)FDI Acoustics, for Radiant Ridge · Tribunal filing · 2026-03-27
- Nordcon 1 technical reports (excerpts from County exhibit 3R)BASE Land & Environmental, filed by the County of Wetaskiwin · Tribunal filing · April to July 2026
- Wetwin power plant information handout (excerpt from exhibit 16A14)Radiant Ridge Energy Limited · Company disclosure · 2026-04-22
- Radiant Ridge submission on the permit conditions (exhibit 13D)Radiant Ridge Energy Limited · Tribunal filing · 2026-11-05
- County rebuttal on D26/169 (selected pages from exhibit 28R)County of Wetaskiwin · Tribunal filing · 2026-11-19
- Land Use Bylaw 2024/66, sections 9.20 and 10.5County of Wetaskiwin · Municipal record · 2024-12-17, as amended
- Municipal Development Plan 2023/05, section 17.1County of Wetaskiwin · Municipal record · 2023-04-11
- Radiant Ridge project consultation concernsErmineskin Cree Nation · Intervener evidence · 2026-09-14