Research backlog

Research leads

Early leads ADCW is investigating. These are not verified project records.

A lead stays under review until ADCW can verify its identity, current status, location, and supporting sources. Our publication standard.

Illustrative photo: Tima Miroshnichenko / Pexels

Leads may overlap each other or projects already listed. They are excluded from the project map and totals.

Browse by lead type

54 leads under review. This is not a count of separate data centres. Choose a type to explore.

Grid connection requests34 leads

Requests for grid capacity recorded by the Alberta Electric System Operator (AESO). A request does not establish an approved connection or a separate facility.

Grid request

Limited public detail

AESO Lethbridge planning area

Alberta South A.I. Load

Facility identity under review

AESO reporting period: November 2026

P3106 · 400 MW

AESO status
P3106: ISD Under Review; Stage 1
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Identify the applicant and site. A relationship to other Lethbridge-area proposals remains unverified.

Grid request

Under review

Facility location unverified

Balzac Area Load

Facility identity under review

Possible overlap under reviewPossible overlap with the existing CAL-3 proposal. The applicant and parcel have not been cross-referenced in a primary source. The historical 45 MW queue figure is not an additional facility or a verified revision to CAL-3.

AESO reporting period: November 2026

P3075 · 45 MW in the earlier data-load list

AESO status
Reclassified as Distribution Load in November 2026
What the source establishes
AESO's earlier lists classified P3075 as Data Load. The November 2026 list moves the 45 MW request to Distribution Load, so it is excluded from ADCW's data-related grid-request total. Reclassification does not establish cancellation.
What’s still open
Confirm the applicant, site, and actual use. A possible CAL-3 relationship remains unresolved; the request is not assigned to that facility.

Grid request

Limited public detail

AESO Swan Hills planning area

BBPI MPC Gas Data Load

Facility identity under review

AESO reporting period: November 2026

P3283 · 600 MW

AESO status
P3283: Cluster 3; Stage 1
What the source establishes
AESO's November 2026 list records this request in Cluster 3. Its category includes data load alongside generation or storage; the listed MW is the requested load, not the capacity of the associated power plant or battery.
What’s still open
Identify the applicant, site, and computing proposal, and resolve overlap with existing ADCW records. The queue name does not establish ownership, a supply agreement, or a distinct facility.

Grid request

Limited public detail

AESO Calgary planning area

Beacon Langdon requests: Indus relationship under review

Facility identity under review

Possible overlap under reviewThese queue requests may relate to Beacon's existing Indus project. The connection is under review; they do not establish a seventh campus.

AESO reporting period: November 2026

P2928 · 400 MW / P2970 · 1,400 MW

AESO status
P2928: ISD Under Review; Stage 2 / P2970: ISD Under Review; Stage 1
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Find a primary-source cross-reference between P2928, P2970, and Indus's applicant or land parcel, and establish whether the requests represent the same campus, different phases, or another proposal.

Grid request

Limited public detail

AESO Swan Hills planning area

Black Bear Gas Data Load

Facility identity under review

Possible overlap under reviewName-based identity check against Teton's existing Black Bear campus listing. The shared name does not prove a match, and the requested grid load is not added to the campus's separate generation figure.

AESO reporting period: November 2026

P3211 · 200 MW

AESO status
P3211: Cluster 3; Stage 1
What the source establishes
AESO's November 2026 list records this request in Cluster 3. Its category includes data load alongside generation or storage; the listed MW is the requested load, not the capacity of the associated power plant or battery.
What’s still open
Identify the applicant, site, and computing proposal, and resolve overlap with existing ADCW records. The queue name does not establish ownership, a supply agreement, or a distinct facility. The shared Black Bear name is not sufficient to assign this request to Teton's campus.

Grid request

Under review

AESO Brooks planning area

Brooks 121S, Brooks Area, and West Brooks 28S

Facility identity under review

Possible overlap under reviewRelationship review against existing Newell and FingerMotion / Newbit records. Three unique AESO IDs do not establish three additional facilities, and the reviewed records do not establish common ownership.

AESO reporting period: November 2026

P3342 · 18 MW / P3347 · 40 MW / P3343 · 12.5 MW

AESO status
P3342: Active; Stage 1 / P3347: Active; Stage 1 / P3343: Active; Stage 1
What the source establishes
AESO records the same September 14, 2026 filing date for all three requests. The Brooks 121S and Brooks Area points are about 24 metres apart. The West Brooks 28S point is about 8.6 km west of Brooks 121S.
What’s still open
The applicants and facility locations are under review. The reviewed records do not connect these entries to the Newell P3109 request or the FingerMotion/Newbit proposal near Tilley.

Grid request

Under review

AESO Calgary planning area

Calgary A.I. Centre Load

Facility identity under review

AESO reporting period: November 2026

P3078 · 74.9 MW

AESO status
P3078: Active; Stage 2
What the source establishes
The request appeared as three 50 MW steps, then 150 MW in one step. AESO listed 75 MW in May 2026 and 74.9 MW in June 2026. The listed service target is January 15, 2029.
What’s still open
Which applicant and facility does P3078 represent? Its relationship to other Calgary proposals is unverified.

Grid request

Under review

AESO Calgary planning area

Calgary Enterprise A.I. Load

Facility identity under review

AESO reporting period: November 2026

P3077 · 74.9 MW

AESO status
P3077: Active; Stage 2
What the source establishes
The request appeared as two 100 MW steps, then 200 MW in one step. AESO listed 75 MW in May 2026 and 74.9 MW in June 2026. The listed service target is January 15, 2029.
What’s still open
The applicant and facility site are under review. P3077 shares filing and target dates with Calgary A.I. Centre, and the indicative points are about 21 km apart.

Grid request

Limited public detail

AESO Didsbury planning area

Carstairs Technology Park MPC Load

Facility identity under review

AESO reporting period: November 2026

P3101 · 950 MW

AESO status
P3101: ISD Under Review; Stage 2
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Confirm the actual development site, applicant, and permits. The Didsbury planning area does not establish a Carstairs facility.

Grid request

Under review

AESO Fort McMurray planning area

Clearwater Area Data Load

Facility identity under review

AESO reporting period: November 2026

P3338 · 74.9 MW

AESO status
P3338: Active; Stage 1
What the source establishes
AESO lists an active Stage 1 request with a March 13, 2028 target for the 74.9 MW step. The indicative point is in the Regional Municipality of Wood Buffalo.
What’s still open
The applicant and project-specific permit or facility site have yet to be identified.

Grid request

Under review

AESO Calgary planning area

Clearwater Technology Park Data Load

Facility identity under review

AESO reporting period: November 2026

P3157 · 74.9 MW

AESO status
P3157: Active; Stage 2
What the source establishes
AESO lists an active Stage 2 request with a November 20, 2028 service target, later than an October 2027 target in earlier lists.
What’s still open
The applicant, facility site, and any link to the Fort McMurray-area P3338 request remain unverified.

Grid request

Limited public detail

AESO Calgary planning area

Cypress Pine Data Load

Facility identity under review

AESO reporting period: November 2026

P3352 · 200 MW

AESO status
P3352: ISD Under Review; Stage 1
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Identify the applicant, parcel, and any municipal or project-specific filing. The Calgary planning area does not establish a Calgary facility or a relationship to another proposal.

Grid request

Under review

AESO High River planning area

Fulton Data Load

Facility identity under review

Possible overlap under reviewPossible relationship to AmpBase's published Vulcan proposal remains a research hypothesis based on queue timing and requested capacity. Neither an additional AmpBase facility nor a confirmed match has been established.

AESO reporting period: November 2026

P3350 · 74 MW

AESO status
P3350: Active; Stage 1
What the source establishes
AESO lists an active Stage 1 request with a February 1, 2030 service target. Its indicative point is southeast of Indus.
What’s still open
The applicant and parcel remain unverified. Matching capacity and timing with nearby queue entries leave their relationship open.

Grid request

Under review

Mossleigh area, Vulcan County

Georgetown Data Load

Facility identity under review

AESO reporting period: November 2026

P3216 · 72.9 MW

AESO status
P3216: Active; Stage 1
What the source establishes
AESO lists a Stage 1 request filed June 1, 2026, with an August 31, 2029 service target. Its indicative point is roughly 216 metres from the separate Georgetown Solar request, P2396. An October 2026 site plan in Alberta Utilities Commission (AUC) exhibit 30318-X0090, page 2, shows a proposed external-load connection and labels two feeders at Mossleigh 1051S.
What’s still open
Who filed P3216, where would the facility be built, and would it use either feeder? Georgetown Solar's separate 230 MW supply and 1 MW grid-demand request does not identify the data-load customer.

Grid request

Limited public detail

AESO Fort Saskatchewan planning area

GLDC Load Phase 1.1 and Phase 1.2

Facility identity under review

Possible overlap under reviewPossible overlap with the existing Sturgeon / Greenlight development chain. The queue names and separate capacities have not been reconciled with the published campus. An additional facility has not been established.

AESO reporting period: November 2026

P2936 · 970 MW / P3151 · 830 MW

AESO status
P2936: Active; Stage 2 / P3151: ISD Under Review; Stage 2
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Resolve the applicant, actual facility or facilities, and relationship to the Meta and Greenlight development chain. The two requests are shown separately and are not added to the Sturgeon project.

Grid request

Limited public detail

AESO Calgary planning area

High Plains East Industrial Park

Facility identity under review

AESO reporting period: November 2026

P3156 · 300 MW

AESO status
P3156: ISD Under Review; Stage 1
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Establish which development and applicant the request represents. AESO's Data Load classification does not by itself establish a specific data centre.

Grid request

Under review

Location unresolved

High River Data Load

Facility identity under review

Possible overlap under reviewPossible relationship to AmpBase's published Vulcan proposal remains a research hypothesis based on queue timing and requested capacity. The map discrepancy and applicant identity remain unresolved.

AESO reporting period: November 2026

P3349 · 74 MW

AESO status
P3349: Active; Stage 1
What the source establishes
The interactive AESO map shows a point north of High River. The November 2026 downloadable map file places it farther south, and the November workbook assigns the Fort Macleod planning area.
What’s still open
A project-specific filing is needed to resolve the location and identify the applicant.

Grid request

Limited public detail

AESO Caroline planning area

Leedale Data Load

Facility identity under review

AESO reporting period: November 2026

P3066 · 1,864 MW

AESO status
P3066: ISD Under Review; Stage 2
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Identify the applicant, parcel, and local development records. The Caroline planning area does not establish a location in Leedale.

Grid request

Limited public detail

AESO Brooks planning area

Maple Rose Data Load

Facility identity under review

AESO reporting period: November 2026

P3341 · 200 MW

AESO status
P3341: ISD Under Review; Stage 1
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Identify the applicant, parcel, and any municipal or project-specific filing. The Brooks planning area does not establish a facility location or a relationship to other Brooks proposals.

Grid request

Limited public detail

AESO Empress planning area

Nexus East MPC Gas Data Load

Facility identity under review

AESO reporting period: November 2026

P3280 · 600 MW

AESO status
P3280: Cluster 3; Stage 1
What the source establishes
AESO's November 2026 list records this request in Cluster 3. Its category includes data load alongside generation or storage; the listed MW is the requested load, not the capacity of the associated power plant or battery.
What’s still open
Identify the applicant, site, and computing proposal, and resolve overlap with existing ADCW records. The queue name does not establish ownership, a supply agreement, or a distinct facility.

Grid request

Limited public detail

AESO Caroline planning area

Nexus West MPC Gas Data Load

Facility identity under review

AESO reporting period: November 2026

P3282 · 600 MW

AESO status
P3282: Cluster 3; Stage 1
What the source establishes
AESO's November 2026 list records this request in Cluster 3. Its category includes data load alongside generation or storage; the listed MW is the requested load, not the capacity of the associated power plant or battery.
What’s still open
Identify the applicant, site, and computing proposal, and resolve overlap with existing ADCW records. The queue name does not establish ownership, a supply agreement, or a distinct facility.

Grid request

Under review

Conrich area, Rocky View County

North Calgary One, Two, and Three

Facility identity under review

AESO reporting period: November 2026

P2952 · 74.9 MW / P2953 · 74.9 MW / P3112 · 450 MW

AESO status
P2952: Active; Stage 2 / P2953: Active; Stage 2 / P3112: ISD Under Review; Stage 1
What the source establishes
North Calgary One and Two were each listed at 450 MW. Two was at 74.9 MW by September 2025 and One by December 2025. In November 2026, both were active at Stage 2 and their service targets moved from March 26, 2027 to July 2, 2029. Three remains at 450 MW with its service date under review.
What’s still open
Do the three queue entries share an applicant or development? County records for Conrich Station describe industrial land use. A data centre application or facility parcel remains unverified.

Grid request

Limited public detail

AESO Fox Creek planning area

Opal Data Load

Facility identity under review

Possible overlap under reviewPossible overlap with the existing Bitdeer Fox Creek facility at the Opal Power Plant site. The AESO request has not been directly linked to that facility, so its 0 MW grid figure is not a revision to Bitdeer's computing demand.

AESO reporting period: November 2026

P3141 · 0 MW

AESO status
P3141: Active; Stage 1
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Confirm the facility, applicant, and requested-load scope. The possible relationship to Bitdeer Fox Creek and Opal Power Plant remains unverified; a zero grid-load entry does not establish zero on-site demand.

Grid request

Limited public detail

AESO Wabamun planning area

ResiliON MPC Gas Data Load

Facility identity under review

AESO reporting period: November 2026

P3284 · 800 MW

AESO status
P3284: Cluster 3; Stage 1
What the source establishes
AESO's November 2026 list records this request in Cluster 3. Its category includes data load alongside generation or storage; the listed MW is the requested load, not the capacity of the associated power plant or battery.
What’s still open
Identify the applicant, site, and computing proposal, and resolve overlap with existing ADCW records. The queue name does not establish ownership, a supply agreement, or a distinct facility.

Grid request

Limited public detail

AESO Red Deer planning area

Rimbey MPC Gas Data Load

Facility identity under review

AESO reporting period: November 2026

P3281 · 600 MW

AESO status
P3281: Cluster 3; Stage 1
What the source establishes
AESO's November 2026 list records this request in Cluster 3. Its category includes data load alongside generation or storage; the listed MW is the requested load, not the capacity of the associated power plant or battery.
What’s still open
Identify the applicant, site, and computing proposal, and resolve overlap with existing ADCW records. The queue name does not establish ownership, a supply agreement, or a distinct facility.

Grid request

Limited public detail

AESO Calgary planning area

Rocky View Data Center MPC Load

Facility identity under review

AESO reporting period: November 2026

P3116 · 800 MW

AESO status
P3116: ISD Under Review; Stage 2
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Identify the applicant and development parcel, and resolve any overlap with known Calgary-region projects before treating this as another facility.

Grid request

Under review

AESO Sheerness planning area

Sheerness Data Load requests

Facility identity under review

AESO reporting period: November 2026

P3227 · 74.9 MW / P3137 · 800 MW

AESO status
P3227: Active; Stage 1 / P3137: ISD Under Review; Stage 1
What the source establishes
AESO lists the 74.9 MW request at Stage 1 with a February 4, 2028 service target. The separate P3137 request is listed at 800 MW and its indicative point is about 8.3 km away.
What’s still open
A shared applicant, facility, or connection to the Sheerness generating station remains unverified. The shared name does not establish one development, and the capacities are not combined.

Grid request

Under review

AESO Airdrie planning area

Sollair Load

Facility identity under review

AESO reporting period: November 2026

P3126 · 4.99 MW

AESO status
P3126: Active; Stage 2
What the source establishes
AESO previously listed 74.4 MW across two steps of 4.9 MW and 69.5 MW. The July 2026 list shows a single 4.99 MW step. AESO classifies the request as behind the fence, its process for changes to facilities already connected to the transmission system.
What’s still open
Which facility would use the requested load? The data-load customer and any relationship to the separate Sollair solar project are unverified.

Grid request

Under review

AESO Edmonton planning area

Sovereign Cloud Data Load

Facility identity under review

Possible overlap under reviewRelationship to the existing Edmonton Energy and Technology Park proposal remains unverified. The planning area and general computing description do not establish either a match or a separate facility.

AESO reporting period: November 2026

P3174 · 74.9 MW

AESO status
P3174: Active; Stage 2
What the source establishes
AESO lists an active Stage 2 request with a December 31, 2029 service target. The indicative point is west of Edmonton.
What’s still open
The facility and applicant are under review. The reviewed records do not link this request to the northeast Edmonton Energy and Technology Park proposal.

Grid request

Limited public detail

AESO Wabamun planning area

Sundance Data MPC Load

Facility identity under review

AESO reporting period: November 2026

P3136 · 401 MW

AESO status
P3136: ISD Under Review; Stage 1
What the source establishes
AESO's November 2026 list records the requested grid capacity and connection-process status shown here. The entry does not establish a project-specific development permit, a committed connection, construction, or operation.
What’s still open
Identify the applicant and site, and establish any relationship to TransAlta or the Sundance power facilities. A shared name does not establish an electricity-supply agreement.

Grid request

Limited public detail

AESO Stavely planning area

Travers Battery Data Load

Facility identity under review

Possible overlap under reviewName-based identity check against the existing Travers AI campus. A direct relationship is unverified. The battery-plus-data request may include battery charging, so 300 MW is not assigned as additional computing demand.

AESO reporting period: November 2026

P3312 · 300 MW

AESO status
P3312: Cluster 3; Stage 1
What the source establishes
AESO's November 2026 list records this request in Cluster 3. Its category includes data load alongside generation or storage; the listed MW is the requested load, not the capacity of the associated power plant or battery. The requested load may include battery charging; it is not a verified computing-load figure.
What’s still open
Identify the applicant, site, and computing proposal, and resolve overlap with existing ADCW records. The queue name does not establish ownership, a supply agreement, or a distinct facility. A connection to the published Travers AI campus has not been established.

Grid request

Limited public detail

AESO Swan Hills planning area

Ursa Major Gas Data Load

Facility identity under review

AESO reporting period: November 2026

P3326 · 466 MW

AESO status
P3326: Cluster 3; Stage 1
What the source establishes
AESO's November 2026 list records this request in Cluster 3. Its category includes data load alongside generation or storage; the listed MW is the requested load, not the capacity of the associated power plant or battery.
What’s still open
Identify the applicant, site, and computing proposal, and resolve overlap with existing ADCW records. The queue name does not establish ownership, a supply agreement, or a distinct facility.

Grid request

Limited public detail

AESO Seebe planning area

Wildcat MPC Gas Data Load

Facility identity under review

AESO reporting period: November 2026

P3285 · 150 MW

AESO status
P3285: Cluster 3; Stage 1
What the source establishes
AESO's November 2026 list records this request in Cluster 3. Its category includes data load alongside generation or storage; the listed MW is the requested load, not the capacity of the associated power plant or battery.
What’s still open
Identify the applicant, site, and computing proposal, and resolve overlap with existing ADCW records. The queue name does not establish ownership, a supply agreement, or a distinct facility.
Company announcements14 leads

Plans described by companies, with site details, commitments, or project relationships still under review.

Company announcement

Limited public detail

Northern Alberta; site location under review

ALTO Northern Alberta Site 1

Facility identity under review

Research review: September 14, 2026

Company-stated 75 MW

What the source establishes
ALTO describes Site 1 as an Alberta data centre campus beside existing industrial infrastructure, with a 75 MW figure.
What’s still open
Confirm the municipality, parcel, capacity scope, developer's site control, and project-specific permits. The company's approximate map is not a verified facility location.

Company announcement

Limited public detail

Northern Alberta; site location under review

ALTO Northern Alberta Site 2

Facility identity under review

Research review: September 14, 2026

Company-stated 100 MW Phase 1

What the source establishes
ALTO describes Site 2 as an Alberta data centre campus with 100 MW labelled as its first phase.
What’s still open
Confirm the municipality, parcel, capacity scope, developer's site control, and project-specific permits. The company's approximate map is not a verified facility location.

Company announcement

Limited public detail

Northern Alberta; site location under review

ALTO Northern Alberta Site 3

Facility identity under review

Research review: September 14, 2026

Company-stated 100 MW Phase 1

What the source establishes
ALTO describes Site 3 as an Alberta data centre campus with 100 MW labelled as its first phase.
What’s still open
Confirm the municipality, parcel, capacity scope, developer's site control, and project-specific permits. The company's approximate map is not a verified facility location.

Company announcement

Limited public detail

Calgary region; municipality not confirmed

Data District Calgary Region Facility

Facility identity under review

Shared program; site details under reviewPart of the same four-region announcement as the published Olds and Bonnyville records. The 240 MW program total covers all four regions and must not be repeated as capacity for each regional entry.

Research review: September 14, 2026

Site capacity unconfirmed; 240 MW is the four-region program total

What the source establishes
Alberta Major Projects names the Calgary region in Technologies New Energy and Data District's proposed four-region program. The stated 240 MW covers Olds, Bonnyville, Calgary, and Edmonton together.
What’s still open
Identify the facility municipality, parcel, site-specific capacity, and application or permit. The program-level figure is not assigned to this entry, and the provincial map is a placeholder.

Company announcement

Limited public detail

Edmonton region; municipality not confirmed

Data District Edmonton Region Facility

Facility identity under review

Shared program; site details under reviewPart of the same four-region announcement as the published Olds and Bonnyville records. The 240 MW program total covers all four regions and must not be repeated as capacity for each regional entry.

Research review: September 14, 2026

Site capacity unconfirmed; 240 MW is the four-region program total

What the source establishes
Alberta Major Projects names the Edmonton region in Technologies New Energy and Data District's proposed four-region program. The stated 240 MW covers Olds, Bonnyville, Calgary, and Edmonton together.
What’s still open
Identify the facility municipality, parcel, site-specific capacity, and application or permit. The program-level figure is not assigned to this entry, and the provincial map is a placeholder.

Company announcement

Limited public detail

East-central Alberta; municipality under review

FingerMotion / BlueFlare east-central Alberta energy park

Facility identity under review

Possible overlap under reviewRelationship to the existing FingerMotion / BlueFlare program remains unresolved. The announced energy-park scale is not added to the Brooks or Hanna records, and it does not establish another acquired or approved campus.

Announcement date: October 15, 2026

Company-announced up to 500 MW energy park; initial 75 MW phase

What the source establishes
FingerMotion's October 15, 2026 announcement describes a proposed east-central Alberta energy park with on-site gas generation and battery storage for computing customers, conditional on land acquisition, approvals, gas supply, and financing.
What’s still open
Identify the municipality, landowner, parcel, and project-specific applications, and reconcile this program with the company's other campus announcements. The energy-park figure is not verified computing demand.

Company announcement

Limited public detail

Coronation area

FingerMotion Coronation Campus

Facility identity under review

Shared program; site details under reviewA named campus area in the same September 15, 2026 program that includes the published Brooks record. The 99 MW program total is shared across that program, not additional capacity allocated to this entry. The physical site and number of sites here remain unverified.

Announcement date: September 15, 2026

Share of a company-announced 99 MW generation program; site allocation unconfirmed

What the source establishes
FingerMotion's September 15, 2026 release names Coronation among four campus areas in a program of ten proposed 9.9 MW generation and data-hall sites.
What’s still open
The exact site, permits, number of units allocated to this campus, and relationship to later company programs remain unresolved. The program's 99 MW is not capacity assigned to this entry.

Company announcement

Limited public detail

Fox Creek area

FingerMotion Fox Creek Campus

Facility identity under review

Shared program; site details under reviewA named campus area in the same September 15, 2026 program that includes the published Brooks record. The 99 MW program total is shared across that program, not additional capacity allocated to this entry. The physical site and number of sites here remain unverified.

Announcement date: September 15, 2026

Share of a company-announced 99 MW generation program; site allocation unconfirmed

What the source establishes
FingerMotion's September 15, 2026 release names Fox Creek among four campus areas in a program of ten proposed 9.9 MW generation and data-hall sites.
What’s still open
The exact site, permits, number of units allocated to this campus, and relationship to later company programs remain unresolved. The program's 99 MW is not capacity assigned to this entry.

Company announcement

Limited public detail

Vulcan area

FingerMotion Vulcan Campus

Facility identity under review

Shared program; site details under reviewA named campus area in the same September 15, 2026 program that includes the published Brooks record. The 99 MW program total is shared across that program, not additional capacity allocated to this entry. The physical site and number of sites here remain unverified.

Announcement date: September 15, 2026

Share of a company-announced 99 MW generation program; site allocation unconfirmed

What the source establishes
FingerMotion's September 15, 2026 release names Vulcan among four campus areas in a program of ten proposed 9.9 MW generation and data-hall sites.
What’s still open
The exact site, permits, number of units allocated to this campus, and relationship to later company programs remain unresolved. The program's 99 MW is not capacity assigned to this entry.

Company announcement

Limited public detail

Lethbridge County (company disclosure; exact parcel unverified)

NU E Power Lethbridge 2 HPC and Digital-Asset Proposal

Facility identity under review

Announcement date: May 27, 2026

Up to 17 MW of proposed electrical supply for computing

What the source establishes
NU E Power's May 27, 2026 disclosure describes a non-binding letter of intent with Digital Asset Solutions for modular high-performance computing and digital-asset mining at Lethbridge 2 in Lethbridge County.
What’s still open
Confirm a definitive agreement, parcel, development permit, utility arrangements, and current delivery status. The Q3 2026 target in the announcement does not establish commissioning.

Company announcement

Limited public detail

Sturgeon County (developer-stated)

Project North Light

Facility identity under review

Research review: October 22, 2026

Developer-stated 360 MW of computing load

What the source establishes
Project North Light's website describes an early proposal for a 360 MW AI data centre in Sturgeon County. It announces partner discussions and community engagement.
What’s still open
Confirm the legal development entity, parcel, site control, power arrangements, approvals, and distinctness from other Heartland proposals. The website does not establish construction.

Company announcement

Limited public detail

Alberta; project site or sites under review

Radiant Ridge / Nordcon modular data-centre deployment

Facility identity under review

Possible overlap under reviewDeployment identity review alongside the existing Wetaskiwin County permit-backed listing. The 3 MW announcement is not assigned to that permit, and an additional physical facility remains unverified.

Announcement date: November 9, 2025

Company-announced 3 MW of modular data centre capacity

What the source establishes
Radiant Ridge's November 9, 2025 release announces a modular data centre deployment with Nordcon, using on-site gas production. The release does not identify a project parcel.
What’s still open
Determine the site or sites, current delivery status, and relationship to the Wetaskiwin County D26/169 listing. Do not assign the announced 3 MW to that permit or assume another distinct facility.

Company announcement

Limited public detail

Northern Alberta; municipality and site under review

Radiant Ridge northern Alberta 40 MW generation proposal

Facility identity under review

Announcement date: January 9, 2026

Company-announced 40 MW generation; computing demand unconfirmed

What the source establishes
Radiant Ridge's January 9, 2026 release describes a letter of intent with an unnamed producer for northern Alberta gas generation serving computing applications. A later gas-sales agreement was intended.
What’s still open
Identify the counterparty, location, definitive agreements, computing facility, and permitting. The 40 MW generation proposal is not established computing demand or operating capacity.

Company announcement

Limited public detail

Southern Alberta; municipality under review

StratGrid Project Mountain View

Facility identity under review

Shared program; site details under reviewPart of StratGrid's broader announced program. Jet.AI describes Mountain View as a second site, but its exact identity and site-specific capacity remain unresolved. Combined program capacity must not be added to Wheatland.

Disclosure date: July 29, 2026

Site-specific capacity unconfirmed

What the source establishes
Jet.AI's July 29, 2026 securities disclosure identifies Project Mountain View as StratGrid's second southern Alberta site. Its combined long-term scale statement covers Mountain View and Wheatland together.
What’s still open
Confirm the municipality, development parcel, site-specific design, and approvals. The name does not establish a site in Mountain View County, and combined program capacity is not assigned to this site.
Municipal records3 leads

Local agendas, permits, and notices with development details still under review.

Municipal record

Under review

County of Grande Prairie No. 1

County of Grande Prairie May 2026 data processing permit

Facility identity under review

Possible overlap under reviewPermit relationship review alongside the existing Emerson Trail listing. A separate permit number and approval scope do not establish an additional physical data centre.

Permit date: May 13, 2026

Capacity unconfirmed; permit PLDEV20260129

What the source establishes
The County's public timeline records a May 2026 permit for a data processing establishment. The permit identifies SE-15-73-6-W6, Enframe Construction Ltd. as applicant, and R.B. Curry Auto Transport Ltd. as owner.
What’s still open
Identify the operating developer and reconcile this permit with PLDEV20250629 and the buildings-only PLDEV20260127. These are different permit scopes, not proof of three separate data centres.

Municipal record

Under review

Municipal District of Greenview No. 16

Greenview D25-141 Data Processing Centre

Facility identity under review

Agenda date: December 10, 2025

Capacity unconfirmed; municipal file D25-141

What the source establishes
Greenview's December 10, 2025 Municipal Planning Commission agenda identifies a data processing centre under D25-141 at SE-4-62-10-W6M.
What’s still open
Resolve the applicant, decision, current status, and relationship to existing Greenview projects before treating it as another facility.

Municipal record

Under review

City of Wetaskiwin discussions; physical site unverified

Wetaskiwin data centre / renewable energy / greenhouse discussions

Facility identity under review

Possible overlap under reviewA possible overlap with the Wetaskiwin County permit is under review. The City and County are different jurisdictions, so neither a shared development nor a separate facility has been established.

Municipal statement date: March 26, 2026

Capacity unconfirmed

What the source establishes
The City of Wetaskiwin's March 26, 2026 statement acknowledges preliminary discussions involving a data centre, renewable energy, and greenhouses, with no formal application submitted at that date.
What’s still open
Identify the developer, site, and any later application. City discussions do not establish a relationship to the separate Wetaskiwin County permit or Radiant Ridge announcements.
Regulatory records1 lead

Regulator filings or approvals that need further research into the computing facility or current status.

Regulatory record

Under review

Clearwater County / Rocky Mountain House area

WCSB Ram River Data Centres and Isolated Power Plant

Facility identity under review

Approval date: September 23, 2025

84 MW approved generation; computing demand unconfirmed

What the source establishes
AUC records cover WCSB's Ram River isolated gas and steam power plant at SW 2-37-10-W5M, intended to support on-site data centres. Approval 30224-D02-2025 extended the plant's completion deadline to June 30, 2027.
What’s still open
Confirm current ownership, construction completion, and operation of the plant and computing facilities. The 84 MW is generating capacity, not verified computing demand.
Reported leads2 leads

Leads from public reporting that need further primary-source confirmation.

Reported lead

Limited public detail

Grande Prairie region; city or county not resolved

BW Velora Grande Prairie Project

Facility identity under review

Research review: September 14, 2026

Capacity unconfirmed

What the source establishes
BetaKit reports a BW Velora proposal to convert an industrial site in the Grande Prairie region into an AI data centre campus. The reported permitting description has not been tied to a municipal file.
What’s still open
Confirm whether the site is in the city or county, identify the applicant and parcel, and resolve possible overlap with other regional developments.

Reported lead

Limited public detail

Medicine Hat and Redcliff region

BW Velora Redcliff AI Data Center Campus

Facility identity under review

Research review: September 14, 2026

Reported eventual 1,200 MW campus

What the source establishes
BetaKit reports that an investment pitchbook lists BW Velora's Redcliff AI campus near Medicine Hat, seeking financing for an eventual 1.2 GW development.
What’s still open
Locate the pitchbook's supporting project documents, identify the applicant and municipality, and establish a parcel or approval record. The report does not establish approval, financing, or construction.
How to read these leads and sources

Grid figures show requested capacity in megawatts (MW), not operating use or approved data centre capacity. An AESO planning area does not identify a verified municipality or facility site.

An AESO “ISD Under Review” status means the in-service date is under review. Cluster 3 is an assessment group, not Stage 3. “Under review” and “Limited public detail” describe ADCW’s research, not an approval status.

Each tile identifies its source date or reporting period. An undated source uses a clearly labelled research-review date. Possible overlaps and shared programs are labelled on individual leads.