Verified project profile
Sturgeon Data Centre
Meta has announced a CA$13-billion-plus, 1 GW data centre in Alberta's Industrial Heartland. Municipal approvals are in effect and site preparation has begun; the public record reviewed by ADCW does not yet confirm that main facility construction is underway.
Project facts
Core scale, approval, employment and schedule information, labelled by the type of evidence available.
Announced capacity
1 GWMeta's announced data-centre capacity.
Sources [3]Investment
More than CA$13 billionCompany-announced project investment.
Sources [3]Federal funding
None publicly identifiedADCW found no project-specific federal grant, loan or contribution in the reviewed sources. Meta says it is fully funding the new generation and grid infrastructure.
Sources [3], [2]Municipal permit
DP-26-0028Issued June 16, 2026; effective July 7, 2026.
Sources [1]Employment
~3,000 peak construction; 300+ operationalCompany projections, not observed job counts.
Sources [3], [4]Target operation
2028–2029Capital Power expects the initial 250 MW load in the second half of 2028; Sturgeon County lists the data centre as operational in 2029.
Sources [6], [2]General contractor
Frost CollectiveA joint venture of Clark Builders and PCL Construction.
Sources [4], [5]Energy and emissions
Supply agreements and the associated Greenlight power plant are tracked separately from Meta's annual clean-energy matching commitment.
Initial grid supply
250 MWCapital Power disclosed an energy-supply agreement lasting more than 10 years, with service anticipated in the second half of 2028.
Sources [6]Dedicated gas generation
932 MWGreenlight's committed first phase is a combined-cycle natural-gas plant expected in service in the second half of 2030.
Sources [7], [8]Permitted expansion
Up to 1,864 MWThe AUC record describes two stages and full development in 2031.
Sources [7]Natural-gas demand
Approximately 150 million cubic feet/dayPembina's disclosed requirement for the current 932 MW Greenlight project.
Sources [8]Full-build GHG estimate
5.677 million tonnes CO₂e/yearGreenlight's federal filing estimate for the maximum 1,864 MW plant without carbon capture. It is not an estimate for only the current 932 MW phase.
Sources [9]Clean-energy matching
100% annual matching promisedMeta says it will add or contract enough clean energy to match annual electricity use. This accounting commitment does not mean the facility's physical electricity supply is fossil-free at all times.
Sources [3], [8]Water
The cooling design and expected use figures are forward-looking company statements until measured operations data is published.
Cooling design
Closed-loop liquid cooling with dry coolingMeta says the cooling system will require no operational water. This is a design claim; measured use will not exist until operations begin.
Sources [3], [4]Other on-site use
Still requiredMeta identifies construction, facility/domestic use, fire protection and equipment maintenance as continuing water demands.
Sources [3], [4]Public infrastructure
Approximately CA$60 millionMeta says this includes roads and water infrastructure; an itemized public breakdown was not found in the reviewed sources.
Sources [3]Approval and public process
Municipal zoning and permits establish what was approved and how the public could participate.
Land-use approval
Permitted use in Heavy Industrial zoningThe master site development permit establishes the framework for a major data-processing facility across the listed parcels.
Sources [1]Public notice and appeal
Notice posted June 16; deadline July 7, 2026Because this was a permitted-use approval, public appeal rights were narrower than for a discretionary use or variance.
Sources [1]Project open house
Not required by the CountySturgeon County states that data centres are permitted in the applicable industrial zone and a public open house is not required for approval.
Sources [2]Timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
- Public record
Sturgeon County issued a grading permit for site preparation. [2]
- Public record
Master site development permit DP-26-0028 issued. [1]
- Public record
AUC issued its approval decision for the associated Greenlight Electricity Centre. [7]
- Public record
Municipal development permit became effective after the notification period. [1]
- Proponent statement
Meta publicly announced the Sturgeon Data Centre. [3]
- Proponent projection
Main data-centre construction expected to begin, according to Sturgeon County's published timeline. [2]
- Proponent projection
Capital Power expects the initial 250 MW data-centre load to enter service. [6]
- Proponent projection
Sturgeon County expects the data centre to be operational. [2]
- Proponent projection
Committed 932 MW Greenlight gas-generation phase expected in service. [8]
What we still don't know
Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.
- The approved data-centre building area, final campus footprint and phased build schedule were not disclosed in the public records reviewed.
- Expected annual facility electricity consumption has not been publicly quantified beyond the announced 1 GW capacity and supply agreements.
- Expected annual water withdrawal and wastewater volumes have not been published; Meta promises annual disclosure after operations begin.
- A project-specific estimate of operational greenhouse-gas emissions has not been published. The available 5.677 Mt CO₂e/year estimate is for Greenlight's maximum 1,864 MW power-plant buildout.
- The projects Meta will use for its clean-energy matching commitment have not yet been identified publicly.
- An itemized breakdown of the CA$60 million in local infrastructure spending and expected municipal tax revenue was not found in the reviewed sources. General tax treatment and any future public support have not been exhaustively confirmed.
- The public sources give two early service milestones: Capital Power's second-half 2028 load date and Sturgeon County's 2029 operational date. The relationship between those milestones is not yet explained.
Source record
Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.
- Development permit approval notice for 56111 Rge Rd 223
Sturgeon County · Municipal record · 2026-06-16
- Data Centre Development
Sturgeon County · Municipal record · Updated through July 2026
- Breaking Ground on Meta's First Data Center in Canada
Meta · Company disclosure · 2026-07-08
- Meta Sturgeon Data Centre fact sheet
Meta / Sturgeon County · Company disclosure · 2026-07
- Sturgeon Data Centre project site
Sturgeon Data Centre · Company disclosure · Accessed 2026-07-22
- Capital Power Enters Long-term Energy Supply Agreement with Meta in Alberta
Capital Power · Company disclosure · 2026-07-08
- Greenlight Electricity Centre: Proceeding 30261
Alberta Utilities Commission · Regulator · Decision issued 2026-06-25
- Greenlight Electricity Centre final investment decision
Pembina Pipeline Corporation · Company disclosure · 2026-07-02
- Greenlight Electricity Centre Initial Project Description
Impact Assessment Agency of Canada · Federal filing · 2025-07-30
- Meta Data Center
Government of Alberta Major Projects · Government database · Accessed 2026-07-22