Grassland and rolling hills beneath a cloudy blue sky
Evidence profile · Clearwater County

Synapse James River Bridge Data Centre

A proposed 1 GW data centre campus near James River Bridge in Clearwater County.

Illustrative landscape · Sevgi Gümüş / Pexels
← Alberta data centre project list
Developer Synapse Data Center

Near James River Bridge, between Range Road 55 and Highway 22, north of Township Road 344

Synapse’s website describes a site in rural central Alberta. Its handout places the proposed campus near James River Bridge and shows about 580 acres for ten data centre buildings, on-site gas power, a reserve plant, and diesel backup. Clearwater County listed Synapse for a closed-session delegation on November 24, 2026. ADCW found no site-specific permit, power-plant filing, or construction record.

Proposed data centre load1 GWSynapse’s full-build design for ten buildings [1][2]
Proposed coolingClosed loopWater volumes remain unconfirmed [1]
Sound studyPendingDeveloper says it will share the study at an open house [1]
Project stageProposedNo public permit or construction record identified [5]
Proposed on-site gas generation1.4 GWSynapse’s ten 140 MW blocks, plus a separate 140 MW reserve plant [1]
Proposed campus areaAbout 580 acresSynapse’s handout gives the area. Legal boundaries remain unconfirmed. [1]

Where it stands

Developer plansProposedSynapse’s handout describes the campus and its on-site power supply [1]
County processDelegation scheduledThe November 24, 2026 agenda names Synapse. A site-specific permit remains unverified. [3][5]
Power-plant reviewNo public filing identifiedNo James River Bridge AUC proceeding found as of November 25, 2026

Separate approval tracks, not a construction progress bar. Record last verified 2026-11-25.

Want to get involved?

Synapse says it plans to share its studies at an open house. ADCW found no announced date, public hearing, or deadline to comment. See the approval and participation record ↓

Check Clearwater County public notices

Power and emissionsCampus demand, electricity supply, and emissions evidence

Synapse proposes to power the campus with on-site gas generation, a reserve plant, and emergency diesel generators.

Important distinction: The figures show how much electricity Synapse’s proposed equipment could use or supply at full buildout. Actual fuel use and emissions are unknown.

Proposed data centre design load: 1 GW. Synapse’s handout and website describe ten buildings designed for 100 MW each at full buildout. Actual electricity use is unknown. [1][2] Proponent statement

How the campus would get power: Synapse proposes to run it off-gridNon-grid-connectedThe facility has no electrical connection to Alberta's interconnected grid and relies on supply available to the site.It does not directly draw from or send electricity to that grid. Power-plant approvals and local impacts can still matter.Learn more →. Synapse’s website describes dedicated on-site generation. The handout goes further and says the campus would run separately from Alberta’s grid. It also gives ratings for the gas units, the reserve plant, and the diesel fleet. [2][1] Proponent statement

Proposed regular gas generation: 1.4 GW. Synapse proposes ten 140 MW gas-fired units. They would use heat from the turbines to generate additional electricity. The company plans to add units as demand grows and says output would depend on temperature, elevation, and how much electricity the plant itself uses. [1] Proponent statement

Proposed reserve generation: 140 MW. Synapse’s handout lists a separate reserve plant to provide extra power when needed. [1] Proponent statement

Proposed emergency diesel backup: 1.8 GW total rated capacity. Synapse proposes 600 generators rated at 3 MW each and says it would run them for emergencies and testing. [1] Proponent statement

Natural gas supply: Caroline-area producers proposed. Synapse describes long-term supply agreements and a pipeline route that is still under discussion. Suppliers, signed contracts, gas volumes, the route, land access agreements, and approvals remain unconfirmed. [1] Proponent statement

Stack emissions targets: Synapse’s targets for power plant exhaust. Synapse says it is targeting half the benchmarks in its handout. That works out to 12.5 parts per million (ppm) for nitrogen oxides and 25 ppm for carbon monoxide. Synapse targets less than 5 ppm for ammonia and describes volatile organic compounds as trace only. Approved limits and measured concentrations remain unverified. [1] Proponent projection

Air quality and greenhouse gases: Air study and annual emissions figures pending. Synapse proposes burners designed to reduce emissions, equipment to treat the exhaust, and stack monitoring. Its planned study would account for the diesel generators, terrain, weather, and existing air quality. ADCW found no study results, annual greenhouse gas totals, or estimates per unit of electricity generated. [1] Proponent statement

What remains unresolved

How much gas would each phase use, and how often would the reserve plant or diesel generators run? What would that mean for annual emissions and air quality at nearby communities?

Water, cooling, and drainageSupply, demand, wastewater, and servicing

Synapse proposes to recirculate cooling water and use air-cooled condensers at the power plants. How much fresh water the campus would need and what approvals would cover its supply are still unknown. [1]

Cooling design: Details vary by source. Synapse’s website advertises liquid and hybrid cooling. The handout describes recirculating cooling water and air-cooled condensers at the power plants. These descriptions may cover different equipment. Synapse has yet to spell out which systems would serve each part of the campus. [2][1] Proponent statement

Water supply and demand: Water source and volumes unconfirmed. Synapse expects to get water from its gas supplier and says it would avoid drawing directly from the aquifer. It proposes metering and leak detection, and plans for reduced supply during drought. The water balance, authorization, and expected daily and peak water use remain unconfirmed. [1] Proponent statement

Steam-cycle water reuse: Synapse estimates 99% reuse in the power plant’s steam cycle. How much freshwater the full campus would need and how much wastewater it would produce are still unknown. Synapse proposes collecting domestic and industrial wastewater separately. Domestic wastewater could go to an authorized facility or a septic system, if permitted. Options for industrial wastewater include reuse, licensed disposal, or return to the gas supplier. [1] Proponent statement

Runoff and nearby wells: Two stormwater ponds proposed. Synapse would keep runoff away from fuel and chemical handling areas and hold and test it before release. The company says it would assess the effects of grading and removing groundwater during construction. Runoff quality, dischargeWithdrawal, consumption, and dischargeWithdrawal is water taken from a source. Consumption is the portion not returned to the same water system. Discharge is water released after use or treatment.These are different quantities. Check which one a water figure describes before comparing projects.Learn more → approvals, and effects on wetlands and wells remain unverified. [1] Proponent statement

What remains unresolved

Where would the water come from, how much would each phase need in normal and drought conditions, and where would treated wastewater and stormwater go?

Sound at nearby communitiesAssessment evidence, controls, and remaining questions

Synapse describes equipment enclosures, silencers, walls, and berms. The developer says it would share a final sound study at an open house.

Sound at nearby communities: Synapse expects to meet sound limits. Synapse proposes equipment enclosures, silencers, walls, and berms, along with monitoring at the property line. Its planned study would account for nearby industry, nighttime operation, generator testing, and construction phases. ADCW found no published study or predicted sound levels. [1] Proponent projection

Low-frequency sound and hum: Modelling and testing proposed. Synapse plans to assess low-frequency tones from equipment such as transformers and fans, take measurements when the equipment starts up, and investigate persistent reports. The sound levels and effectiveness of the controls remain unknown. [1] Proponent statement

What remains unresolved

What sound levels would nearby communities experience overnight and during generator testing? Would the assessment account for existing industrial noise and low-frequency sound?

Land, wetlands, and wildlifeSite area and the available environmental record

Site and access: About 580 acres. Synapse’s website says rural central Alberta and lists 500+ acres. The handout gives a more specific estimate of about 580 acres and sketches the campus between Range Road 55 and Highway 22, north of Township Road 344. It shows entrances off Township Road 344 and Highway 22. It lists 53003 Highway 587, James River Bridge, as the visit and contact address. [1][2] Proponent statement

Proposed structures and setback: Ten buildings up to 30 ft tall. The plan shows two rows of data centre buildings around the power plants, support buildings, and two stormwater ponds. It lists a 112 ft stack. Synapse says the setback would exceed 600 metres. The distance and any finding of compliance remain unverified. [1] Proponent statement

Outdoor lighting: Shielded fixtures and poles up to 25 ft. Synapse plans to direct lights downward, use warm lighting at 3,000 K or lower where practical, and dim lights to 10% when full brightness is unnecessary. It says lights that aren’t needed would switch off or dim by 11 p.m. in spring and summer and 9 p.m. in fall and winter. How much light would reach nearby properties is still unknown. [1][6] Proponent statement

What remains unresolved

Which parcels would the campus occupy, and from what points did Synapse measure the claimed setback of more than 600 metres? How much light and construction traffic would reach nearby properties and roads?

Indigenous contextTreaty geography, engagement, and consultation evidence

Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.

Treaty geography: Proposed parcels still unverified. Alberta’s treaty boundary dataset provides regional context. Synapse’s handout gives an approximate campus location, and ADCW has yet to confirm the legal parcels or the proposed gas pipeline route. Treaty maps alone cannot identify all First Nations and Métis communities whose rights or land use could be affected. [8][1] ADCW context

First Nations and Métis engagement: No project-specific consultation record identified. ADCW found no public record of which First Nations or Métis communities have been contacted, what concerns they raised, or how Synapse or the responsible authorities responded. ADCW context

What remains unresolved

Which First Nations and Métis communities could be affected by the campus and the gas pipeline? What land and water uses need to be considered, which communities have been engaged, and how would their concerns be addressed?

Approvals and participationSeparate decisions, public participation, and the recorded timeline

ADCW found no public site-specific Alberta Utilities Commission (AUC) filing, municipal permit, or construction record for the James River Bridge proposal as of November 25, 2026.

Clearwater County Council: Closed-session delegation scheduled. Clearwater County’s November 24, 2026 agenda names Synapse Data Center at item 9.1. The agenda gives no site or permit number. The outcome remains unverified. [3] Public record

AESO connection list: No request linked to this site. The Alberta Electric System Operator’s November 2026 connection list contains no entry ADCW could link to the proposal. Synapse’s handout describes an electrical system separate from Alberta’s grid. [1][4] ADCW context

Developer outreach: Open house proposed. Synapse says it plans to share its noise, air, and water studies and speak directly with landowners. ADCW found no open-house date or public hearing notice. [1][5] ADCW context

Emergency planning: Safety measures and emergency drills proposed. Synapse describes shutoffs, spill containment, firefighting water, and coordination with local responders for incidents involving fuel, ammonia, or batteries. It says it would test the plan before operation and review it as new power units open. An approved response plan or agreement with local responders remains unverified. [1] Proponent statement

Earlier Olds proposal: Separate site and proceeding. On August 17, 2026, the Alberta Utilities Commission denied Synapse’s proposed power plant in Olds in Decision 30732-D01-2026. [9] Public record

Recorded timeline

Observed decisions and future dates are kept distinct; projected milestones may change.

November 24, 2026. Clearwater County’s council agenda scheduled a closed-session delegation from Synapse Data Center. The public agenda gives no outcome. [3] Public record

November 25, 2026. ADCW reviewed Synapse’s undated handout on the proposed campus. [1] ADCW context

What remains unresolved

Which permit applications will be filed, when will the supporting studies be public, and when can people review them and comment?

Company and commitmentsScale, projected benefits, and delivery commitments

Jobs Synapse projects: 2,000+ jobs at peak construction. Synapse estimates at least 300 full-time-equivalent roles at the data centre and about 30 to 45 at the power plant during operations. The company has not confirmed how many would be local hires. [1] Proponent projection

Public costs and revenue: Synapse says it would finance the project privately. The company expects municipal and provincial tax revenue and says the campus would cost taxpayers nothing and would have no subsidized grid costs. Public costs, expected tax revenue, financing, and any infrastructure agreements remain unverified. [1] Proponent projection

County-owned fibre network: Open-access network. Clearwater County documents its own open-access fibre project. [7] Public record

Synapse’s proposed fibre role: Potential wholesale customer. Synapse says buying wholesale fibre service would bring revenue to the county. A signed service agreement and commercial terms have yet to be confirmed. [1] Proponent projection

Proposed community benefits: No binding commitments identified. The handout proposes annual local grants, school and trades programs, developer-funded road, intersection, and broadband upgrades, and public reporting on water, air, noise, hiring, and grants. ADCW found no signed agreement, committed budget, or delivery schedule. There is no confirmed basis yet for counting these as benefits the community would receive. [1] Proponent statement

Project overview

Synapse proposes a 1 GW data centre campus on about 580 acres near James River Bridge in Clearwater County. The campus would be built in stages, with its own natural-gas power and diesel backup. Site approvals remain unconfirmed.

What remains unresolved

Who would pay for roads, intersections, emergency services, and fibre connections? What would Synapse commit to in a signed agreement, who could enforce it, and how would residents see whether the commitments were met?

Unresolved questions are retained within each relevant topic above.

SourcesOriginal documents and publication details

Source record

Company disclosures establish what the company said, not independent verification of projected outcomes.

  1. Community information handoutSynapse Data Center · Company disclosure · Undated; reviewed November 25, 2026
  2. Synapse Data Center campus overviewSynapse Data Center · Company disclosure · Accessed 2026-11-25
  3. November 24, 2026 Clearwater County Council agenda, item 9.1Clearwater County · Municipal record · 2026-11-24
  4. AESO Connection Project Reporting, November 2026 listAlberta Electric System Operator · Regulator · 2026-11-03
  5. Clearwater County public noticesClearwater County · Municipal record · Accessed 2026-11-25
  6. Clearwater County Land Use Bylaw 25/050Clearwater County · Municipal record · Amended May 2026
  7. Clearwater County BroadbandClearwater County · Municipal record · Accessed 2026-11-25
  8. Treaty Boundary datasetGovernment of Alberta · Government database · Accessed November 25, 2026
  9. Synapse Data Center Power Plant Project in OldsAlberta Utilities Commission · Regulator · 2026-08-17