Travers AI Data Centre Campus
A proposed AI campus near Travers Reservoir: January 2026 concept up to 2 GW; current website describes up to 1 GW long term.
Vulcan County rezoned 594.55 acres on June 17, 2026. Palliser Grid's current website describes a 10 MW first phase, compared with four 500 MW phases in the January 2026 concept. Both current company pages agree on 10 MW for Phase 1; ADCW's November 13, 2026 review recorded about 400 MW on the earlier power page. The current roadmap remains unreconciled with the January 2026 IT-load concept. A project-specific development permit, construction, and the judicial review outcome remain unverified.
Where it stands
Separate approval tracks, not a construction progress bar. Record last verified 2026-11-15.
The filing scheduled the originating application for September 29, 2026. No outcome, later court date, or current public participation window was verified in this review. Palliser Grid's community page dated November 9, 2026 says its Lomond office is open for questions; check the company page for visit details. See the approval and participation record ↓
Power and emissionsCampus demand, electricity supply, and emissions evidence
Palliser Grid's current website describes planned stages of 10 MW, 100 MW, and 300 MW, followed by a long-term ambition of up to 1 GW. As retrieved November 15, 2026, the power page agrees with the homepage on a 10 MW first phase. ADCW's November 13, 2026 review recorded approximately 400 MW on the earlier power page. The January 2026 concept remains a separate, unreconciled IT-load design. Its current homepage describes a 240 kV connection strategy and a preliminary AltaLink screen for up to 600 MW of demand service, meaning electricity delivered to the site. That screening figure is not an approved connection or an operating load.
Important distinction: The January 2026 concept targeted up to 2,000 MW of IT load. The website now describes a different staged roadmap, but does not reconcile it with the earlier IT-load target. All capacity figures remain proposals or preliminary screening information.
Current staged roadmap: 10 MW, 100 MW, and 300 MW stages; up to 1 GW long term. The stages are not added together, and the page does not establish that these are IT-load figures comparable with the January 2026 concept. [1] Proponent projection
First-phase design history: Current 10 MW; earlier power page about 400 MW. The power page retrieved November 15, 2026 agrees with the homepage. ADCW recorded about 400 MW on the earlier power page in its November 13, 2026 review. The relationship to the January 2026 2 GW IT-load concept is still unresolved. [1][2] ADCW context
January 2026 IT-load concept: Up to 2,000 MW. The earlier plan divided full buildout into four potential 500 MW phases. Retained as design history, not an additional current capacity claim. [7] Proponent projection · Historical proposal
Grid connection concept: Current 240 kV strategy; earlier 500 kV concept. The company homepage describes a preliminary AltaLink screen for up to 600 MW of demand service, reported from August 2026 materials. The underlying screen was not independently verified. The January 2026 plan proposed a 500 kV substation and two feeds. Neither establishes a completed connection agreement or approval. [7][1] Proponent projection
Phase-one battery concept: 2,400 MWh. The January 2026 plan proposed a four-hour lithium iron phosphate battery system. The current company power page still discusses storage but does not confirm this earlier sizing. [7] Proponent projection · Historical proposal
Emergency generationBackup generationBackup generators provide electricity when the normal supply is unavailable. They may also run for testing or maintenance.Installed capacity does not establish continuous operation, annual fuel use, or emissions. Operating hours and permit conditions are separate evidence.Learn more →: Diesel backup proposed; total unresolved. The January 2026 concept contains backup and IT-load figures that do not align consistently across sections. A reconciled design for the current roadmap was not found. ADCW does not publish a single backup total. [7] ADCW context
What remains unresolved
How the current 10 MW first phase and up-to-1-GW roadmap relate to the earlier approximately 400 MW first-phase description and January 2026 2 GW IT-load concept; final grid studies, connection scope, and approvals.
A reconciled emergency-generation design, fuel inventory and air-emissions estimate.
Water, cooling, and drainageSupply, demand, wastewater, and servicing
Palliser Grid's water page, dated November 9, 2026, says it holds an approved Bow River Irrigation District (BRID) allocation of up to 5,500 acre-feet per year. ADCW has not independently verified an allocation agreement or regulatory authorization. This is a company-reported allocation ceiling, not forecast or measured water use. The January 2026 concept proposed reservoir supply and wastewater reuse; the current company page says closed-loopClosed-loop coolingCooling fluid circulates repeatedly through a contained loop instead of being routinely discharged after one pass.That describes the loop, not the whole site's water use. A separate heat-rejection system can still use water, and filling, maintenance, and leaks also matter.Learn more → and dry-cooling options remain under evaluation, with no final cooling configuration or operating consumption figure. [7][3]
Water allocation claim: Company reports up to 5,500 acre-feet per year. The company water page dated November 9, 2026 says BRID approved this allocation. ADCW has not independently verified the agreement, its conditions, or regulatory authorizations. This annual ceiling is not operating consumptionWithdrawal, consumption, and dischargeWithdrawal is water taken from a source. Consumption is the portion not returned to the same water system. Discharge is water released after use or treatment.These are different quantities. Check which one a water figure describes before comparing projects.Learn more → and is excluded from the daily-demand total. [3] Proponent statement
Proposed source and cooling: Reservoir supply; cooling design unresolved. The January 2026 concept proposed Travers Reservoir supply and wastewater reuse. The company water page says closed-loop and dry-cooling options remain under evaluation; no final consumption figure is claimed. [7][3] Proponent projection
Reuse concept: On-site wastewater treatment and cooling reuse. The January 2026 plan proposed treating and reusing water. The current company water page still leaves the final water balance and operating agreement unresolved. [7][3] Proponent projection
Comparable daily volume: Not yet defensible. The claimed annual allocation is not a consumption forecast. No final operating water balance was found, so ADCW does not turn the annual ceiling into daily operating demand. [7][3] ADCW context
What remains unresolved
Independent confirmation and conditions of the claimed BRID allocation, applicable water authorizations, infrastructure ownership, and final operating water balance.
Final stormwater studies remain unresolved.
Sound at nearby communitiesAssessment evidence, controls, and remaining questions
Project-specific sound evidence: Not publicly disclosed. Project-specific sound details were not found in the public sources reviewed. A predicted sound level is not a measurement from an operating facility. ADCW context
What remains unresolved
Final noise studies remain unresolved.
Land and site layoutSite footprint and the planning information in the record
Concept scale: About 8 million square feet. The January 2026 plan described approximately 20 to 30 data centre buildings. The current website does not reconcile that earlier footprint with its staged roadmap. [7] Proponent projection
Rezoned land: 594.55 acres. Council's final June 2026 amendment was smaller than the 865-acre area described at the earlier public-hearing stage. [8][6] Public record
What remains unresolved
Final traffic, habitat, and cumulative-effects studies remain unresolved.
Indigenous contextTreaty geography, engagement, and consultation evidence
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty geography: Treaty 7 territory. This geographic label does not establish which First Nations or Métis communities may be affected, whether project-specific consultation occurred or what positions communities hold. The company community page dated November 9, 2026 says project-led Indigenous engagement had not begun and claims no consultation, agreement, partnership, or endorsement. That dated company statement does not establish the current status of Crown consultation. [10][4] ADCW context
What remains unresolved
A project-specific Indigenous consultation and engagement record.
Approvals and participationSeparate decisions, public participation, and the recorded timeline
Land-use decision: Rezoning approved June 17, 2026. The decision changed 594.55 acres from Rural General to Rural Industrial so a development-permit application can be considered. [8] Public record
Public hearing: Completed. The County received submissions before returning the bylaw to Council for decision. [6] Public record
Judicial review: Recorded application date: September 29, 2026. The applicant alleges procedural fairness failures in the rezoning process and asks the Court of King's Bench to quash the decision. The filing alleges that the County approved an incomplete application, changed material available for public feedback without further engagement, and disclosed relevant planning information only after the public hearing. Vulcan County and Eric Steeves, operating as Palliser Grid, are named as respondents and were expected to respond. The allegations are not adjudicated findings in this record. The scheduled date has passed; a hearing outcome or subsequent decision is not verified here. A project-specific development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more → and separate utility, water, and environmental decisions would still be required. [9] Public record
Data centre development permit: Not verified in reviewed records. Vulcan County's notices page and its three current November 2026 approval notices did not establish a permit for this campus. That is not proof that no application exists. Rezoning permits an application; it does not authorize construction. [6][8][5] ADCW context
Recorded timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
January 2026. Palliser Grid submitted the rezoning application and campus concept to Vulcan County. [7] Public record
April and June 2026. Vulcan County held public-hearing stages on proposed Bylaw 2026-007. [6] Public record
June 17, 2026. Council approved amended rezoning for 594.55 acres. [8] Public record
July 22, 2026. The owners of Condominium Plan 9311680 filed a judicial review application alleging procedural fairness failures in the rezoning process. Vulcan County and Eric Steeves, operating as Palliser Grid, are named as respondents. The allegations have not been adjudicated. [9] Public record
September 29, 2026. The filing scheduled the originating application in the Court of King's Bench of Alberta. The date has passed; no outcome or subsequent court date was verified as of November 13, 2026. [9] Public record
Second quarter of 2027. The January 2026 concept targeted construction start, subject to approvals and project decisions. This earlier target was not confirmed by the current website. [7] Proponent projection
Second quarter of 2029. The January 2026 concept targeted first-phase service. The company's current website does not announce a launch date. [7] Proponent projection
As of November 13, 2026. Palliser Grid's homepage describes a 10 MW first phase and up to 1 GW long term, while its power page still describes about 400 MW for Phase 1. The company also reports a BRID allocation and a closed first capital round. These statements do not establish construction or operation, and their announcement dates were not verified. [1][2][3] Proponent statement
As of November 15, 2026. The power page now agrees with the homepage on a planned 10 MW first phase, followed by 100 MW and 300 MW stages and up to 1 GW long term. The earlier approximately 400 MW first-phase description and January 2026 2 GW IT-load concept remain design history. No permit, court outcome, or operating milestone is established by this website change. [1][2] Proponent statement
What remains unresolved
Whether Vulcan County will receive and approve a project-specific development permit.
The outcome and timing of the judicial review application challenging Bylaw 2026-007.
Company and commitmentsScale, projected benefits, and delivery commitments
Earliest phase-one service: Second quarter of 2029. An earlier target in the January 2026 concept plan, not a verified current delivery commitment. The current website does not announce a launch date. [7] Proponent projection
Employment estimate: Up to 1,000 construction; about 200 operations. These are estimates in the January 2026 concept. The company community page dated November 9, 2026 says it is not publishing employment figures yet; the earlier estimates are not current commitments. [7][4] Proponent projection
Company funding statement: First capital round reported closed. The company homepage describes the round as fully funded and oversubscribed, but does not disclose the amount or investors. This does not establish financing for the full campus. [1] Proponent statement
Operating team: Craig Stenhouse named Operating Partner. Palliser Grid identifies Eric Steeves as founder and Craig Stenhouse as Operating Partner. These roles do not establish an operating facility. [1] Proponent statement
Project overview
A proposed AI campus on 594.55 rezoned acres near Travers Reservoir. The January 2026 concept targeted up to 2 GW of IT load; Palliser Grid's homepage and power page now describe a 10 MW first phase and up to 1 GW long term. ADCW's November 13, 2026 review recorded an approximately 400 MW first phase on the earlier power page. The current pages agree on the first phase; the January 2026 2 GW IT-load concept remains unreconciled with the newer roadmap. Rezoning allows a development-permit application; construction, a project-specific permit, and the outcome of the judicial review remain unverified.
What remains unresolved
Committed customers, the amount and scope of the reported first capital round, full-project financing, final investment decision, and binding construction schedule.
Unresolved questions are retained within each relevant topic above.
SourcesOriginal documents and publication details
Source record
Company disclosures establish what the company said, not independent verification of projected outcomes.
- Palliser Grid project roadmap, site readiness, and teamPalliser Grid · Company disclosure · Accessed 2026-11-15
- Power stewardship: current 10 MW first-phase roadmap; earlier approximately 400 MW description retained as historyPalliser Grid · Company disclosure · Updated 2026-11-09; accessed 2026-11-15
- Water stewardship: company-reported BRID allocation and cooling optionsPalliser Grid · Company disclosure · Updated 2026-11-09; accessed 2026-11-15
- Community stewardship: employment and Indigenous engagement statementsPalliser Grid · Company disclosure · Updated 2026-11-09; accessed 2026-11-15
- Current development notices (reviewed with DP 66-2026, 67-2026, and 68-2026)Vulcan County · Municipal record · Accessed 2026-11-13
- Public Hearing Scheduled for Bylaw 2026-007Vulcan County · Municipal record · Updated 2026-06
- Travers AI Data Centre Campus concept planPalliser Grid / Vulcan County · Municipal record · 2026-01
- Council Highlights: June 17, 2026Vulcan County · Municipal record · 2026-06-17
- Originating Application: The Owners, Condominium Plan 9311680 v. Vulcan County and Eric Steeves, operating as Palliser GridCourt of King's Bench of Alberta · Court filing · Filed 2026-07-22
- Treaty Boundary datasetGovernment of Canada Open Government Portal · Government database · Modified 2026-06-29