Verified project profile
Travers AI Data Centre Campus
Palliser Grid has submitted a concept for a hyperscale AI data centre campus with a planning target of up to 2,000 MW of IT load. Vulcan County approved industrial rezoning for 594.55 acres in June 2026, allowing the proponent to apply for a development permit. The rezoning is now challenged through a judicial review application, and the allegations have not been adjudicated. The rezoning does not approve the data centre, transmission infrastructure, water use or construction.
Project facts
Core scale, approval, employment, and schedule information, labelled by the type of evidence available.
Planning target
Up to 2,000 MW of IT loadThe concept uses four potential 500 MW phases. This is not approved demand.
Sources [2]Concept scale
About 8 million square feetThe plan describes approximately 20 to 30 data centre buildings at full buildout.
Sources [2]Rezoned land
594.55 acresCouncil's final June 2026 amendment was smaller than the 865-acre area described at the earlier public-hearing stage.
Sources [3], [1]Earliest phase-one service
Second quarter of 2029A target in the concept plan, subject to approvals, interconnection, financing and construction.
Sources [2]Employment estimate
Up to 1,000 construction; about 200 operationsThese are planning estimates rather than employment commitments.
Sources [2]Energy and emissions
The concept describes a new 500 kV substation, two transmission feeds, a large battery system and diesel emergency generation. None of those elements should be read as built, contracted or finally approved.
IT load
Up to 2,000 MWA full-build planning target, divided into four potential 500 MW phases.
Sources [2]Grid connection concept
New 500 kV substation and two feedsThe plan references AESO and AltaLink processes but does not show a completed connection agreement or approval.
Sources [2]Phase-one battery concept
2,400 MWhThe plan proposes a four-hour lithium iron phosphate battery system. Final sizing and approval are not established.
Sources [2]Emergency generationBackup generationBackup generators provide electricity when the normal supply is unavailable. They may also run for testing or maintenance.Installed capacity does not establish continuous operation, annual fuel use, or emissions. Operating hours and permit conditions are separate evidence.Learn more →
Diesel backup proposed; total unresolvedThe concept contains backup and IT-load figures that do not align consistently across sections. ADCW does not publish a single backup total until they are reconciled.
Sources [2]Water
The concept proposes water from the Bow River Irrigation District through Travers Reservoir and reuse of treated wastewater. Final demand, allocation, licence changes and infrastructure agreements remain unresolved. [2]
Proposed source
Travers Reservoir / BRIDThe concept anticipates an agreement and possible licence amendment. It does not establish an approved allocation.
Sources [2]Reuse concept
On-site wastewater treatment and cooling reuseThe plan proposes treating and reusing water, but a final campus water balance was not published.
Sources [2]Comparable daily volume
Not yet defensibleThe plan gives efficiency assumptions but not enough internally consistent, approved information for ADCW to add a daily volume to the province-wide total.
Sources [2]Noise
Project-specific noise evidence is shown when it is available. A predicted sound level is not a measurement from an operating facility.
Project-specific noise evidence
Not publicly disclosedProject-specific noise details were not found in the public sources reviewed.
Indigenous context
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. This section brings together the public record on treaty geography, Indigenous ownership, consultation, and community concerns. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty geography
Treaty 7 territoryThis geographic label does not establish which First Nations or Métis communities may be affected, whether project-specific consultation occurred or what positions communities hold. The reviewed municipal concept does not provide a complete consultation record.
Sources [5]Approval and public process
The rezoning is now subject to a judicial review application alleging procedural fairness failures, including that Vulcan County approved an incomplete application, changed material available for public feedback without further engagement, and disclosed relevant planning information only after the public hearing. The allegations have not yet been adjudicated. The application is scheduled for September 29, 2026. Vulcan County and Eric Steeves, operating as Palliser Grid, are named as respondents and are expected to respond. A project-specific development permit and separate utility, water and environmental decisions would still be required.
Land-use decision
Rezoning approved June 17, 2026The decision changed 594.55 acres from Rural General to Rural Industrial so a development-permit application can be considered.
Sources [3]Public hearing
CompletedThe County received submissions before returning the bylaw to Council for decision.
Sources [1]Judicial review
Application scheduled September 29, 2026The applicant alleges procedural fairness failures in the rezoning process and asks the Court of King's Bench to quash the decision. Vulcan County and Eric Steeves, operating as Palliser Grid, are named as respondents. The allegations have not been adjudicated.
Sources [4]Data centre development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more →
Not issuedRezoning permits an application; it does not authorize construction.
Sources [1], [3]Timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
- Public record
Palliser Grid submitted the rezoning application and campus concept to Vulcan County. [2]
- Public record
Vulcan County held public-hearing stages on proposed Bylaw 2026-007. [1]
- Public record
Council approved amended rezoning for 594.55 acres. [3]
- Public record
The owners of Condominium Plan 9311680 filed a judicial review application alleging procedural fairness failures in the rezoning process. Vulcan County and Eric Steeves, operating as Palliser Grid, are named as respondents. The allegations have not been adjudicated. [4]
- Public record
The originating application is scheduled in the Court of King's Bench of Alberta. The filing seeks an order moving the matter to Special Justice Chambers and judicial review of the rezoning decision. [4]
- Proponent projection
The concept targets construction start, subject to approvals and project decisions. [2]
- Proponent projection
The concept targets first-phase service. [2]
What we still don't know
Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.
- Whether Vulcan County will receive and approve a project-specific development permit.
- The outcome and timing of the judicial review application challenging Bylaw 2026-007.
- The final AESO connection request, system studies, transmission route and AltaLink approvals.
- A reconciled emergency-generation design, fuel inventory and air-emissions estimate.
- The approved water allocation, licence amendments, infrastructure owner and full campus water balance.
- A project-specific Indigenous consultation and engagement record.
- Committed customers, financing, final investment decision and binding construction schedule.
- Final noise, traffic, stormwater, habitat and cumulative-effects studies.
Source record
Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.
- Public Hearing Scheduled for Bylaw 2026-007
Vulcan County · Municipal record · Updated 2026-06
- Travers AI Data Centre Campus concept plan
Palliser Grid / Vulcan County · Municipal record · 2026-01
- Council Highlights: June 17, 2026
Vulcan County · Municipal record · 2026-06-17
- Originating Application: The Owners, Condominium Plan 9311680 v. Vulcan County and Eric Steeves, operating as Palliser Grid
Court of King's Bench of Alberta · Court filing · Filed 2026-07-22
- Treaty Boundary dataset
Government of Canada Open Government Portal · Government database · Modified 2026-06-29