Meaningful movement, plainly explained

ADCW Weekly

New records, material evidence, hearings, decisions, and significant project changes. Small site fixes and routine housekeeping stay out of the bulletin.

Current edition

ADCW Weekly

WHAT'S NEW

Junction 42 AI research lab proposed near Penhold

Red Deer County announced a land purchase offer for Lot 24 and a required rezoning process for an estimated $300 million AI research lab.

Why it matters: A public hearing and developer open house are expected. Rezoning would not itself approve the data centre; power, water, and noise details remain unverified.

View project →

Hanna Campus #1 conditional purchase agreement and revised design

FingerMotion announced an agreement executed September 30, 2026, with 60 days of due diligence and closing scheduled after conditions are waived. Its revised concept proposes 3 MW of grid supply and 3 MW of on-site gas generation.

Why it matters: The new design replaces the earlier 9.9 MW concept. A purchase agreement and proposed power mix do not establish completed ownership, permits, or operation.

View project →

Power arrangements and explanations beside project terms

Visit the How It All Works section to understand grid connections, behind-the-meter generation, tethered generation, and temporary bridging. Question-mark help explains relevant power, cooling, water, approval, and evidence terms within profiles and expanded listings.

Why it matters: Readers can check what a term means without leaving the project. On-site generation does not necessarily mean off-grid, and a closed cooling loop does not establish zero water use.

Visit How It All Works →

Ewing Lake data-processing approval revoked

ADCW corrected the listing after reviewing the August 22, 2025 Tribunal decision, which revoked approval of the Bitcoin-mining use while preserving the power-generation approval with revised conditions.

Why it matters: This is a correction based on an older decision, not a new September ruling. The proposal is now Inactive; the preserved 9.9 MW power component does not authorize data processing or establish operation.

View project →

Past editions

ADCW Weekly

WHAT'S NEW

FingerMotion Brooks Campus #1 acquisition agreement

FingerMotion disclosed a conditional US$2.3 million acquisition of Newbit, including existing site rights, permits, and fixed infrastructure.

View project →

ADCW Weekly

WHAT'S NEW

Edmonton Energy & Technology Park planning amendment

Edmonton is reviewing Stantec's application for Walton Global Investments to allow data centres and associated power generation in the park's Medium Industrial Precinct and redesignate about 625 acres.

View project →

Armada Nowlit Clive proposal

Lacombe County identifies the application parties and confirms rezoning must come before a development permit. The developer now describes dry cooling, off-site wastewater servicing, and a 36.0 dBA modelled nighttime total at the closest assessed home.

View project →

County of Newell data centre bylaw

The County held a public hearing on proposed Bylaw 2129-26 on September 10, 2026. Its September 24, 2026 Council agenda listed a petition about the bylaw but no third reading.

View project →

ADCW Weekly

WHAT'S NEW

Boreal Technology Hub at Keephills

Parkland County now calls the Keephills proposal Boreal Technology Hub. BGRE will lead development for Brookfield and CPP Investments and host an October 7, 2026 open house.

View project →

ADCW Weekly

WHAT'S NEW

FingerMotion Hanna Campus #1

FingerMotion says its Hanna subsidiary signed a binding letter of intent for land at 409 Pioneer Trail South for a proposed 9.9 MW power-and-compute site.

View project →

ADCW Weekly

WHAT'S NEW

Emerson Trail data centre permit

The County of Grande Prairie issued development permit PLDEV20250629 on September 4, 2026, for a data processing establishment in the Emerson Trail Industrial Area.

View project →

Woodcote cryptocurrency facility

Big Lakes County has approved permit 26-D0053 for a cryptocurrency-mining facility on an existing oil and gas lease north of Lesser Slave Lake Narrows.

View project →

ADCW Weekly

WHAT'S NEW

Alberta power generation map layer

The project map now includes an optional CODERS layer with 210 Alberta generation facilities, their installed capacity, generation source, and snapshot status.

View map →

ADCW Weekly

WHAT'S NEW

Kakwa cryptocurrency project

A new profile documents a proposed data-processing centre of up to 9.9 MW paired with an AUC-approved 8.40 MW isolated natural-gas plant in Greenview.

View project →

ADCW Weekly

WHAT'S NEW

Meta Sturgeon permit appeal

A September 15, 2026 filing asks the Land and Property Rights Tribunal to let challenges to the Project Frost master permit proceed to a full hearing.

View project →

ADCW Weekly

WHAT'S NEW

Travers AI Data Centre Campus

A July 22, 2026 judicial review application challenges Vulcan County's rezoning decision and is scheduled for September 29, 2026.

View project →

FingerMotion Alberta program

FingerMotion says it is advancing ten separate 9.9 MW sites across Brooks, Coronation, Fox Creek, and Vulcan, totalling 99 MW of gross generation.

View project →

ADCW Weekly

WHAT'S NEW

Fire Technology Torrington

Kneehill County approved two additional units in April 2026 for the existing 9.5 MW cryptomining facility near Torrington.

View project →

Fire Technology Ewing Lake

County permit DP 24097 conditionally approved nine gas generators totalling 9.9 MW and nine Bitcoin-mining containers.

View project →

Athill Carbon-area data centre

Municipal and AUC records document a data centre paired with 9.97 MW of approved natural-gas generation southwest of Carbon.

View project →

Pathfinder Rocky 5

The 60 MW approved Bitcoin-mining power project is now tracked with Pathfinder and MCK's court-appointed receivership.

View project →

ADCW Weekly

WHAT'S NEW

Armada Nowlit Wabasca / Hoole

A new Rule 007 filing proposes a 19.8 MW on-site natural-gas facility serving nine co-located data-centre units.

View project →

ADCW Weekly

WHAT'S NEW

StratGrid Project Wheatland

An SEC-filed Jet.AI disclosure identifies a proposed Wheatland County campus designed around approximately 200 MW of on-site natural-gas generation.

View project →

Gayford and Clive record correction

Gayford is now a separate proposed record. AUC proceedings 30385, 30476, and 30709 were removed from Clive and assigned to the 19.95 MW Gayford facility.

View project →

eStruxture CAL-3

AUC Proceeding 31020 seeks approval for 21 diesel emergency standby generators totalling 66.75 MW at CAL-3.

View project →

ADCW Weekly

WHAT'S NEW

2661707 Alberta Ltd. Greenview sites

Municipal records show eight effective permits for modular data processing centres on existing gas-well footprints. A ninth application remains deferred.

View project →

FingerMotion Brooks Campus Zone

FingerMotion announced a binding memorandum to acquire land rights and permitting for a first 9.9 MW behind-the-meter site in the County of Newell.

View project →

Data District Bonnyville

Alberta's Phase 1 record names Bonnyville as the expected second of four regional projects in a combined 240 MW program led by Data District and Technologies New Energy.

View project →

ADCW Weekly

WHAT'S NEW

Alberta natural-gas policy

Alberta says industrial proponents have raised concerns about access to large quantities of natural gas and that it is working with industry and infrastructure owners on possible solutions.

View issue →

ADCW Weekly

WHAT'S NEW

Beacon Saunders Lake

New municipal evidence confirms the 160-acre land-use change. The County said on June 26 that it had approved no data-centre development permits.

View project →

Wild Rose Power Hub

A new evidence profile explains the plan under review, developer cooling claims, and conflicting job figures.

View project →

Beacon Foothills

The profile now explains the amended plan’s wetland and wildlife evidence and further checks required before disturbance.

View project →

Prairie Sky Strathmore

The listing now separates the company’s elapsed Q2 2026 opening target and phased roadmap from verified project progress.

View project →

ADCW Weekly

WHAT'S NEW

Beacon Indus

The AUC oral hearing for the proposed 1.494 GW natural-gas power plant has been held, and a decision is still pending.

View project →

Goldfinch Technology Park

Wheatland County's final plan confirms the area concept plan was adopted and places technology centres in a Medium Industrial policy area.

View project →

AESO Bring Your Own Generation

The AESO delayed final rules and application intake for its Bring Your Own Generation process until fall 2026.

View issue →

Prairie Sky Strathmore

Prairie Sky now publishes a staged path from a 2 MW retrofit to 50 MW and says it is designing for direct liquid cooling.

View project →