Independent. Publicly sourced. Alberta focused.

See where Alberta's data centre buildout is happening.

Explore verified projects, understand their potential impacts, and follow what has changed.

Project explorer

Data centre projects across Alberta

Verified project dataEvery record with a verifiable site is mapped. Treaty geography is a best-effort match between available boundary information and each project's published location. It provides geographic context only and does not identify affected communities or consultation.
Electricity system contextTurn on the transmission and power generation layers to explore Alberta's mapped electricity infrastructure near data centre projects. Proximity does not confirm a project connection or available supply.Learn how to read these layers →

Use +/− or your keyboard to zoom. Hold Ctrl while scrolling, or use two fingers on touchscreens.

Verified records
80
56 active + 20 operating + 4 inactive
Active buildout
56
Used for the forward-looking totals below
Municipalities
40
Across all verified records in 10 Alberta regions

ADCW inventory scope: The project-demand, generation, and water summaries above cover 56 proposed, approved, and under-construction projects. The 20 operating facilities and 4 inactive proposals remain in the full directory, but are excluded from those summaries so existing use is not mixed with proposed new demand. The separate AESO explorer below covers its broader connection-request list.

Transmission lines across a rural landscape at sunset.

Why should I care?

Large data centre campuses create new electricity demand. Meeting it can require dedicated power plants, gas pipelines, substations, cooling systems, and water infrastructure built alongside the server buildings.

Power · AESO connection requests

How much grid power is being requested?

The Alberta Electric System Operator (AESO) tracks applications for grid connections. This number adds the requested grid capacity of its data-related entries, including projects paired with gas generation or batteries.

Open AESO's full dashboard ↗

Data-related grid connection requests

27.6 GW

62 AESO entries · 27,646.29 MW requested

All included areas, stages, and statuses

Requested capacity, not power currently being used or a total approved for connection. 1 GW = 1,000 MW.

Start with all requests, then narrow by area, connection stage, or status. The number, bars, and entry list update together.

AESO November 2026 project list. Verified November 4, 2026.

Monthly project list verified by ADCW. Use Refresh data to check for a newer map update.

Included: Data Load, Gas + Data Load, Battery + Data Load, and Cogen + Data Load. Recently Cancelled entries are excluded.

Counted: AESO's Total DTS (Demand Transmission Service), the requested addition to grid-load capacity. Supply capacity is excluded. Entries are not a count of distinct campuses; battery hybrids may include charging load.

Where do these requests stand?

AESO statuses describe how requests are being handled. They are not consecutive phases or guarantees of approval.

Active

The accepted request is progressing through assessment or connection work. Some connection phases may already be in service; this is not a statement that the whole facility is operating.

2.2 GW23 entries

ISD Under Review

AESO is reconsidering the requested in-service date, meaning when the connection would become available. The request has not been cancelled.

21.1 GW30 entries

Cluster 3

The request is in AESO's third group of projects being assessed together. This applies to qualifying generation or storage projects, including data-related hybrids. The 3 identifies the group, not Stage 3.

4.3 GW9 entries

Status amounts use the selected area and stage, before the status filter. All included statuses are selected on first load. AESO's status definitions ↗

What do the numbered connection stages mean?

Stage is progress through the grid-connection process. The route varies by project type; these are short summaries, not data-centre approval or construction labels.

Stage 1: Scope / preliminary assessment
Define the connection and studies needed. Cluster projects receive a preliminary grid assessment.
Stage 2: Assessment / detailed studies
Study grid effects, connection options, and costs. Cluster projects undergo detailed assessment.
Stage 3: Regulatory preparation
Prepare connection designs, agreements, and required regulatory applications.
Stage 4: Regulatory review
The Alberta Utilities Commission reviews required connection applications. Approval is not automatic.
Stage 5: Grid construction
Build the connection infrastructure and prepare to energize it. This does not establish the data centre's construction status.
Stage 6: Connection close-out
Bring the connection into service and complete final requirements. The facility's commercial operation date can differ.

AESO's process guides ↗

See the entries behind this number (62)
AESO entry names and requested load. Filters apply to this table and the headline number.
AESO entryPlanning areaType / statusStageRequested MW
P2926 Beacon Foothills A.I. Hub LoadHigh RiverData Load
ISD Under Review
2400
P2927 Beacon Harry Smith A.I. Hub LoadWabamunData Load
ISD Under Review
2400
P2928 Beacon Langdon A.I. Hub LoadCalgaryData Load
ISD Under Review
2400
P2934 Beacon Heartland A.I. Hub LoadFort SaskatchewanData Load
ISD Under Review
2400
P2935 Beacon Saunders Lake A.I. Hub LoadEdmontonData Load
ISD Under Review
2400
P2936 GLDC Load Phase 1.1Fort SaskatchewanData Load
Active
2970
P2942 Genesee Data Center 1 MPC LoadWabamunData Load
ISD Under Review
21,000
P2946 Genesee Data Center 2 MPC LoadWabamunData Load
ISD Under Review
2500
P2952 North Calgary One Data Centre MPC LoadCalgaryData Load
Active
274.9
P2953 North Calgary Two Data Centre MPC LoadCalgaryData Load
Active
274.9
P2970 Beacon Langdon A.I. Hub 2 LoadCalgaryData Load
ISD Under Review
11,400
P3066 Leedale Data LoadCarolineData Load
ISD Under Review
21,864
P3077 Calgary Enterprise A.I. LoadCalgaryData Load
Active
274.9
P3078 Calgary A.I. Centre LoadCalgaryData Load
Active
274.9
P3079 Captus LoadGlenwoodData Load
Active
374.9
P3083 Keephills Data Centre Phase 1.1WabamunData Load
ISD Under Review
2230
P3095 Keephills Data Centre Phase 2WabamunData Load
ISD Under Review
2466
P3101 Carstairs Technology Park MPC LoadDidsburyData Load
ISD Under Review
2950
P3102 Goldfinch Technology Park MPC LoadStrathmore/BlackieData Load
ISD Under Review
2950
P3106 Alberta South A.I. LoadLethbridgeData Load
ISD Under Review
1400
P3107 Chestermere Enterprise A.I. LoadCalgaryData Load
ISD Under Review
1400
P3108 Wild Rose Power Hub LoadCalgaryData Load
ISD Under Review
21,300
P3109 Newell Data Center MPC LoadBrooksData Load
ISD Under Review
21,200
P3110 Mihta Askiy Data LoadPeace RiverCogen + Data Load
ISD Under Review
1300
P3112 North Calgary Three Data Centre MPC LoadCalgaryData Load
ISD Under Review
1450
P3114 Banshee Data MPC LoadHinton/EdsonData Load
Active
374.9
P3116 Rocky View Data Center MPC LoadCalgaryData Load
ISD Under Review
2800
P3126 Sollair LoadAirdrieData Load
Active
24.99
P3136 Sundance Data MPC LoadWabamunData Load
ISD Under Review
1401
P3137 Sheerness Data MPC LoadSheernessData Load
ISD Under Review
1800
P3141 Opal Data LoadFox CreekData Load
Active
10
P3151 GLDC Load Phase 1.2Fort SaskatchewanData Load
ISD Under Review
2830
P3152 Keephills Data Centre Phase 1.2WabamunData Load
ISD Under Review
1165
P3156 High Plains East Industrial ParkCalgaryData Load
ISD Under Review
1300
P3157 Clearwater Technology Park Data LoadCalgaryData Load
Active
274.9
P3174 Sovereign Cloud Data LoadEdmontonData Load
Active
274.9
P3175 Beacon Heartland Data LoadFort SaskatchewanData Load
ISD Under Review
1400
P3198 Lynx Data LoadFort SaskatchewanData Load
ISD Under Review
11,800
P3204 Lynx Data Load Phase 2Fort SaskatchewanData Load
ISD Under Review
11,800
P3211 Black Bear Gas Data LoadSwan HillsGas + Data Load
Cluster 3
1200
P3216 Georgetown Data LoadStrathmore/BlackieData Load
Active
172.9
P3227 Sheerness Data LoadSheernessData Load
Active
174.9
P3236 AEC Mill 844S Data LoadHigh PrairieData Load
Active
160
P3248 Banshee MPC Data Load ReliabilityHinton/EdsonData Load
Active
10
P3280 Nexus East MPC Gas Data LoadEmpressGas + Data Load
Cluster 3
1600
P3281 Rimbey MPC Gas Data LoadRed DeerGas + Data Load
Cluster 3
1600
P3282 Nexus West MPC Gas Data LoadCarolineGas + Data Load
Cluster 3
1600
P3283 BBPI MPC Gas Data LoadSwan HillsGas + Data Load
Cluster 3
1600
P3284 ResiliON MPC Gas Data LoadWabamunGas + Data Load
Cluster 3
1800
P3285 Wildcat MPC Gas Data LoadSeebeGas + Data Load
Cluster 3
1150
P3312 Travers Battery Data LoadStavelyBattery + Data Load
Cluster 3
1300
P3326 Ursa Major Gas Data LoadSwan HillsGas + Data Load
Cluster 3
1466
P3338 Clearwater Area Data LoadFort McMurrayData Load
Active
174.9
P3341 Maple Rose Data LoadBrooksData Load
ISD Under Review
1200
P3342 Brooks 121S Data LoadBrooksData Load
Active
118
P3343 West Brooks 28S Data LoadBrooksData Load
Active
112.5
P3347 Brooks Area Data LoadBrooksData Load
Active
140
P3348 Vulcan Data LoadStavelyData Load
Active
174
P3349 High River Data LoadFort MacleodData Load
Active
174
P3350 Fulton Data LoadHigh RiverData Load
Active
174
P3352 Cypress Pine Data LoadCalgaryData Load
ISD Under Review
1200
P3353 EA Link Data LoadFort SaskatchewanData Load
Active
174.9
Source, filters, and limits

The saved figures are checked against AESO's monthly project list and public connection-project map service, linked from its connection project reporting page. AESO publishes its project list monthly. The verified monthly snapshot appears on page load. Refresh data optionally checks the map service for a newer update; if a complete response cannot be verified, the displayed data stays in place. Unfamiliar categories or possible data-related requests outside the selected categories require review before the live total can update.

All included statuses and connection stages are counted by default. Status descriptions follow AESO's project-list guide; stage summaries follow its independent assessment, cluster assessment, and connection processes.

Connection, Cluster, and Behind the Fence (BTF) entries are included where they have a data-related type. Zero-MW entries remain in the entry count. Cogen means combined heat and power. The mixed gas, battery, and cogen types are included to avoid dropping data-related requests simply because they include supply or storage.

This is a source-defined request queue, not ADCW's verified project inventory, approved connections, operating use, or an estimate of every Alberta data centre. Off-grid proposals may be absent. Do not add this total to generation capacity or to ADCW's separately curated project-demand total. AESO's full dashboard opens with its own controls; these filters are not passed to Power BI.

Old scale versus new scale

An operating facility and a proposed campus

At their published capacities, Beacon Indus would equal about 480 times Qu Edmonton EDM1's electricity capacity.

2.5 MWQu Edmonton EDM1Operating facility capacity

≈ 480×the electricity capacity

1.2 GWBeacon IndusProposed campus capacity

Each small mark represents the capacity of one Qu Edmonton EDM1 facility. This compares published electricity capacity, not building sizes, actual use, or a count of Indus buildings. Indus is proposed. 1 GW = 1,000 MW.

Why electricity capacity matters

About 10.5 terawatt-hours (TWh) in one year

If a facility drew 1.2 GW continuously for a year, it would use slightly more electricity than was delivered across Calgary in all of 2025.

This illustrates the proposed maximum at full demand every hour, not the project's expected or actual use. ENMAX reports 9.8 TWh delivered in Calgary in 2025.

One portfolio: 4.5 GW. Beacon's announced six-site Alberta portfolio alone equals about 44% of Alberta's 2025 average demand. Portfolio announcement, not operating demand or a guarantee that every site will be built.

Meeting new data centre demand can require dedicated power plants, gas pipelines, substations, cooling systems, and water infrastructure alongside the server buildings.

Putting water demand in human terms

What does 13.8 million L/day mean?

1 m³1,000 L

This total comes from only 5 of 56 active projects.It combines comparable projected or proposed daily water volumes, including water published for related power plants. It is not measured province-wide use.

This comparison uses Alberta's 2021 residential average of 195 litres per person per day, the latest province-wide figure published by Statistics Canada. It compares volume only and does not mean the project water is potable, comes from a municipal system, or is entirely consumed.View the Statistics Canada data.

Read the label, not just the number. Water licensed, withdrawn, consumed, and returned describe different things.

About the project

Evidence before rhetoric.

Alberta Data Centre Watch is an independent public-interest project that makes fragmented information about Alberta data centre development easier to find, compare, and understand.

ADCW is not affiliated with any government, regulator, municipality, political party, or project proponent. It tracks material data centre infrastructure across AI, hyperscale, high-performance computing, colocation, cryptocurrency, and other workloads, plus directly related power infrastructure when the connection can be documented. Ordinary internal server rooms fall outside the current scope.

Primary sources come first. Company and government claims are attributed to the people making them. Unknown information stays visible, and every material summary should lead back to an original record.

Read how ADCW verifies Alberta data centre projects →